In a project network, the project completion time has been determined to be a random variable with a mean of 52 days and a standard deviation of 5 days (and can be assumed to be Normally distributed). How many days should we allow for this project to have approximately 99% probability of completion?

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91869719
  • Price:- $10

Priced at Now at $10, Verified Solution

Have any Question?


Related Questions in Operation Management

Choose two product categories egcars explain what is

Choose TWO product categories (e.g.cars). Explain what is positioning? Plot TWO perceptual maps using the positioning bases outlined in the textbook. Each perceptual map should have at least FIVE different brands on it. ...

Virtual product development vpdthe stage gate product

Virtual Product Development (VPD) The Stage Gate Product Development Process was developed during the 1980’s by Dr. Cooper. Many functional societies, highly innovative management consultants and individual company drive ...

Please type the answer1 why does the us export less to

Please Type the answer 1. Why does the U.S. export less to Mexico than to Canada, when the U.S. and Mexico differ more in comparative advantages than the U.S. and Canada? 2. In what way is product life cycle theory flawe ...

Selling building partnerships 9th edition castleberry

SELLING: BUILDING PARTNERSHIPS 9TH EDITION CASTLEBERRY/ TANNER One question in 3 parts A. What is the term used to describe the action of a negotiation team member who tries to begin the negotiation during the preliminar ...

1 why do some companies industries and cultures have

1. Why do some companies, industries, and cultures have different "CSR Thresholds"? Illustrate your answer with examples for all three categories. 2. (a) Develop a plan to prevent cheating and plagiarism in online classe ...

1 discuss two strategies that can be used for leading

1. Discuss two strategies that can be used for leading change. How do these strategies increase stakeholder support and create momentum for a change initiative to be successful? Why might you want to consider including t ...

Tanner park is a small amusement park that provides a

Tanner Park is a small amusement park that provides a variety of rides and outdoor activities for children and teens. In a typical summer season, the number of adult and children’s tickets sold are 20,000 and 10,000, res ...

Many supermarkets and other large retailers now offer

Many supermarkets and other large retailers now offer self-checkout systems that encourage customers to scan, pay for, and bag their merchandise themselves. These systems allow the store to place employees in other areas ...

Assignment business functionsoverviewthe assignment

Assignment : Business Functions Overview: The assignment provides an opportunity for you to perform research, build your knowledge about the School of Business and professional business functions, and practice profession ...

1 why is trust important in a project how can lack of trust

1. Why is trust important in a project? How can lack of trust affect the project, team, and stakeholders? How can a project manager establish trust among the project team and stakeholders? Illustrate with an example (eit ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As