In a PERT project network, an activity has an optimistic estimate of 8 weeks, a pessimistic estimate of 24 weeks, and a most-likely estimate of 10 weeks. What is the expected time for this activity?
10.0 weeks
10.33 weeks
4.16 weeks
12.0 weeks
none of the above