In 2015, Reynolds Construction Company received a contract to construct a water purification system for the city of Oakmont. By January of 2016,work was nearly complete on the main system; however, it was apparent that work on a special remote control building would have to be finished earlier than originally planned if the main system was to be completed on time.

Mr. James Alison, field construction supervisor for Reynolds had arranged a meeting with Mr. Henry Phillips, project engineer, to restudy the arrow diagram of their critical path schedule for the construction of the remote control building in an effort to determine the shortest possible time in which the job could be done without spending more money than necessary.

Reynolds uses PERT as a tool to assist in project planning and control. A list of the activities and predecessors for the remote control site are shown in Exhibit 1. The cost table, Exhibit 2, lists the activities, their normal costs and their expected durations (te), optimistic (min required) durations (to), and pessimistic durations (tp).

The sequence of consecutive activities requiring the longest time to complete before the end of the project is known as the "critical path" for that project. The path is considered "critical" because any delay in that particular sequence will delay the completion of the entire project.

Exhibit1.

Job Label

Job Description

Immediately Preceding Jobs

A

Procure Materials

Start

B

Prepare site

Start

C

Prepare request for Oakmont Engineering Department approval

Start

D

Prefabricate building and deliver to site

A

E

Obtain Oakmont Engineering Department approval

C

F

Install connecting lines to main system

A

G

Erect building and equipment on site

B, D, E

Exhibit 2: Cost and Time Table for Remote Control Building Project

Activity

Activity Cost(for expected time duration)

Max Possible Time (weeks)

Expected Time (weeks)

Min Possible Time (weeks)

Crash cost/week

A

$5,000

4

3

2

$5,000

B

$14,500

8

6

4

$6,000

C

$2,500

3

2

1

$2,500

D

$10,000

7

5

3

$4,000

E

$8,000

3

2

2

---

F

$11,500

8

7

5

$3,000

G

$10,000

6

4

2

$7,000

Total cost of completing the entire project is $61,000, assuming no activities are crashed. Any crash costs must be added to that amount. Note that Activity E cannot be expedited.

Part 1

1. Draw a PERT diagram of this building project. Label all nodes and indicate all activity duration times.

2. What is the critical path?

3. How long will it take to complete the project without crashing?

4. What is the associated cost of the entire project?

5. Revise the schedule in order to complete the project within 10 weeks.

6. Indicate the new cost and critical path (or paths).

Part 2

Suppose Reynolds is proceeding on the 10-week cost schedule (that you determined in parts 1e and 1f above). [To meet the 10-week schedule in Part 1e, you had to crash one or more activities. Here, you start with that schedule that you determined after you crashed these activities - or activity. You can NOT go back and ‘uncrash' activities. Once you pay the money to shorten an activity, you can't go back and ‘unshorten' it.] It becomes obvious that it will take not two but five weeks to prepare the necessary data for the request for Oakmont approval and that this step alone will now cost $7,000. (Assume that activity C cannot be crashed down from 5 weeks for parts a, b or c.)

1. What steps would you take to keep on the 10-week schedule ?

2. What would be your new critical path or paths?

3. What would happen to project costs?

Part 3

You've got the project expedited to 10 weeks and then, in usual fashion, the higher-ups tell you to get it down to 6 weeks *.

1. Is it possible to expedite the project to finish it in 6 weeks? Show why or why not.

2. If there is a penalty cost of $10,000 per week for every week the project is late beyond 6 weeks, what action would you take? Be specific. What activities would you crash - how many weeks would you crash them and/or for how many weeks would you incur a penalty? What is the associated cost of the entire project given your actions? If you provide just generalizations here, you will receive no credit.

*Activity C, the preparation for approval, will take two weeks as described in the case and can be crashed for this question.

Part 4

Go back to Question 1b - before you revised the schedule to complete the job in 10 weeks (meaning you've not crashed any activities to finish the job in 10 weeks). What is the probability of completing this building project in 9 weeks?

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91972336
  • Price:- $20

Priced at Now at $20, Verified Solution

Have any Question?


Related Questions in Operation Management

1 discuss the purpose and major elements of a synopsis for

1. Discuss the purpose and major elements of a synopsis for a formal report. 2. Discuss the difference in the planning process for a solicited versus unsolicited business proposal. 3. Discuss how mobile devices have chan ...

1 identify an organization that faced a crisis of some type

1. Identify an organization that faced a crisis of some type that was highly publicized. How did the organization address the crisis? What specifically did they do once it was evident a crisis was afoot? 2. Why is it cri ...

1 the paper itself should address whether you believe that

1. The paper itself, should address whether you believe that companies like NIKE that secure manufacturing, sourcing or supply chain support in less developed areas of the globe are obligated to ensure that the workers t ...

Directionsstudents will conduct an analysis on the current

Directions Students will conduct an analysis on the current state of the compensation system and address pay-for-performance and benefits. Reference should be made to individual and group incentives, performance appraisa ...

Competencyexamine the nature and functions of strategic

Competency Examine the nature and functions of strategic management. Instructions Today a new quarter begins at one of the following well-known organizations: Google, Walt Disney Company, Amazon, P&G, 3M, or Ford Motor C ...

1 to make merit pay a true incentive managers musta limit

1) To make merit pay a true incentive, managers must: A. limit the number of people in the company’s executive management team. B. pay out a maximum of about 2% as a merit pool each year. C. avoid giving “all A’s” so tha ...

1 write a four paragraph movie analysis on the film gung ho

1. Write a four paragraph movie analysis on the film "Gung Ho", a 1986 comedy film. Note: it must be based on a marketing perspective 2. Find a company that has executed a global expansion strategy taking advantage of th ...

One criticism of both the product cost percentage and

One criticism of both the product cost percentage and contribution margin methods used for determining menu prices is that both are based primarily on the cost of food (or beverage) and ignore the cost of labour. In many ...

Interview a manager an owner or a president of a business

Interview a manager, an owner, or a president of a business. Discuss with this person the strategies he or she uses to ensure customer satisfaction. How does service quality enter into the strategies, or does it? Find ou ...

As the chief operating officer for post corporation you

As the Chief Operating Officer for Post Corporation, you receive many requests from current and former employees for letters of recommendation. Yesterday, you received an e-mail request to write a letter of recommendatio ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As