Q. Suppose the length of critical path in a project is 40 days also the criterion deviation is 2 days. Illustrate what due date should be set for the project so that the probability of completing the project is 95percent? Round the answer to the nearest higher integer.
Q. Illustrates what are the Identification also description of human implications, potential resistance factors also the drivers of the change.