Q. OM 334 task seconds tasks that must precede
A 20 -
B 7 A
C 20 B
D 22 B
E 15 C
F 10 D
G 16 E,F
H 8 G
the workday is seven hrs long. Demand for completed to product is product is 750 per day.
a) Find the cycle time.
b) Illustrate what is the theoretical number of workstations?
c) Draw the precedence diagram.
d) Balance the line using sequential restrictions also the longest-operating-time rule also the longest following task.
e) Illustrate what is the efficiency of the line balanced as in d?
f) Suppose the Demand rose from 750 to 800 units per day. Illustrate what would you do? Show any amount or calculations.
g) Suppose that Demand rose from 750 to 1,000 units per day. Illustrate what would you do? Show any amount or calculations.