Q. If it is known that seven men can build nineteen boats in eleven weeks.
Illustrate what is the productivity?
Elucidate how many workers require to be recruited in order to complete 85 boats in 26 weeks?
Elucidate how long should it take for 8 workers to complete 132 boats?
Elucidate how many boats could 27 workers build in 32 weeks?
Illustrate what is the main assumption that requires holding true in order for these computed answers to be valid?