Q. The PV was $1,700, the EV is $1,850, also the AC is $2,100, so we have a CV of $-250 also an SV of $150." So you tell your boss exactly which. Illustrate what does the above tell you about this project, also explain how would you tell the boss? Illustrate what else do you need to know also illustrate what actions might you take next?