Q. Discussion Questions:
1. Develop a network drawing for Hill Construction also Conclude the critical path. Explain how long is the project expected to take?
2. Illustrate what is the probability of finishing in 270 days?
3. If it were necessary to crash to 250 or 240 days, explain how would Hill do so also at illustrate what costs? As noted in the case, Assume which optimistic time estimates can be used as crash times