Q. Product A is an end item also is made from two units of B also four of C. B is made of three units of D also two of E. C is made of two units of F also two of E. A has a lead time of one week. B, C, also E have lead times of two weeks, also D also F have lead times of three weeks.
a. Show bill of materials (product structure tree).