Ask Operation Management Expert

HYDROSUB’S UNFLOATABLE AMPHIBIOUS ASSAULT VEHICLE

Kathleen Johnson started her new job as chief buyer at Hydrosub in San Francisco. Her day was without incident until she received the following telephone call. Voice on phone: Good afternoon, Ms. Johnson. I am Burt Lauderas, project supervisor at Bolger Shipyards in Tacoma. The design changes for the A.A.V. are not part of our current contract. We need to renegotiate the contract before instituting the changes. Completion of the A.A.V. will be delayed an additional four weeks. Kathleen Johnson (mildly concerned): Is it really necessary to renegotiate the current contract before beginning the work? Voice on phone: Yes, Ms. Johnson, the contract states that every design change must be renegotiated. Kathleen Johnson (more concerned): Why will it take four additional weeks to complete the project? Voice on phone: It will take time to renegotiate the contract and hire replacement welders, and approximately two weeks to do the rework. Kathleen Johnson (completely bewildered): Thank you for calling, Mr. Lauderas. I’ll contact you tomorrow. After recovering her composure, she opened the A.A.V. file and started the formation of her first ulcer. Status reports showed that progress toward completion had been slow. The last chief buyer had been “retired” when costs exceeded the original estimate of $9 million. Revised cost estimates revealed expected expenditures to exceed $23 million. Particularly despairing was the fact that the completion date had already been revised four times and the current completion date was listed as “unknown. After hours of reviewing the A.A.V. project file, Kathleen understood Burt Lauderas’s concerns. The project involved building a prototype amphibious assault vehicle for the U.S. government. It had been Hydrosub’s intent to build a premium product, without concern for cost. If Hydrosub received the subsequent production contract, the company’s financial stability would be greatly enhanced. However, due to in-house capacity problems, Bolger Shipyards had been contracted to build the prototype. Hydrosub engineers designed the prints and specifications for the prototype. These specifications incorporated the latest in high tech design and utilized the best materials available. Design specifications had changed innumerable times over the project’s life. Continual rework and time delays had hampered progress. Bolger had reported design errors that necessitated the refitting of complex equipment and rework of the aluminum welding. Materials requirements included the use of welded aluminum. Bolger normally employed only steel welders; aluminum welders were in short supply and impatient during work stoppages. On the A.A.V. project, Bolger Shipyards currently employed 150 people on two shifts. Often Bolger required overtime work. The Bolger contract was cost-based plus a fixed fee. A particularly disturbing problem was Bolger’s cost reporting system. Bolger contract negotiators waited for up to three weeks for cost data. Weekly time cards, bimonthly reporting, and periodic analysis greatly hindered preparation for the contract talks. As Kathleen Johnson reflected on the facts, her phone rang again. Voice on phone: Hello, Ms. Johnson, welcome to Hydrosub. This is George Rope, president of Hydrosub. Kathleen Johnson: Thank you, Mr. Rope. 205 George Rope: Mr. Johnson, I feel uneasy burdening you with the Bolger Shipyards problem, but I haven’t any other choice. Your hiring was based on your tremendous qualifications. We had hoped to acclimate you to your responsibilities; unfortunately, there is no time. The A.A.V. project must be concluded soon. Over 100 Hydrosub employees are currently working on this project; they are discouraged. The government is very anxious, and we are competing for the future sales of this product. Utilize all your expertise and finish the prototype.

1. Who is responsible for the poor performance of the Bolger contract?

2. What caused the production delays and cost miscalculations?

3. What can Kathleen Johnson do now to ensure completion of the project and prevent further problems?

4. How should Hydrosub’s staff have prepared for negotiations with suppliers on this contract?

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M93086164

Have any Question?


Related Questions in Operation Management

Conflictdefine functional versus dysfunctional conflict in

Conflict Define functional versus dysfunctional conflict in a work group and explain how you can increase functional conflict and decrease dysfunctional conflict. Develop a response that includes examples and evidence to ...

For this assignment you will need to find 2 articles in

For this assignment, you will need to find 2 articles in business that can help describe what are IT strategic initiative being undertaken by an organization are like. Choose a different organization for each of the arti ...

Coping with problems joe is a little nervous he has just

Coping With Problems Joe is a little nervous. He has just been transferred from another plant to take over a production line. Production is down and there is a serious problem with absenteeism. To make matters worse, the ...

Over 30 years ago michael porter identified a holistic

Over 30 years ago Michael Porter identified a holistic approach to understanding how competitive forces shape strategy. He posited that the only way to truly insulate an organization from underlying economic volatility i ...

You are the contracting officer for an air-to-ground

You are the contracting officer for an air-to-ground missile development program. A contract for pre-production models of the missile was awarded by your predecessor and the contractor is behind schedule. In a program me ...

The ikea case provides an excellent opportunity to apply

The IKEA case provides an excellent opportunity to apply strategic management concepts to a large privately-held company that is expanding into India. IKEA is a Netherlands-based Swedish company with a presence in 44 cou ...

Can you answer for me the following questions about social

Can you answer for me the following questions about social loafing and the three main causes of free-riding. 1. Give a description of the phenomenon of social loafing. 2. Give a description of the phenomenon of free-ridi ...

1 analyzing the bridgestonefirestone and ford motor company

1. Analyzing the Bridgestone/Firestone and Ford motor company, is it sufficient to use the ISO/QS 9000 standards as the main basis of vendor/product selection? 2. What position to these cars company ( 1. Volkswagen, 2. F ...

Research the effect of primary and secondary seat belt laws

Research the effect of primary and secondary seat belt laws on the occurrence of motor-vehicle injuries and fatalities. Explain how epidemiologic studies influenced the development of current seat belt laws. Describe how ...

Please provide a brief paragrap of the key takaways from

Please provide a brief paragrap of the key takaways from each of the following topics: Designing Clear Visuals in business reports Designing Successful Documents and Websites Writing Winning Proposals

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As