Huston Power, Inc., (HPI), an electrical power-generating company, has hired your firm to refurbish one of its gas turbine units. The manufacturing department works only on the day shift. The staff of the manufacturing department is paid on an hourly basis and is paid one-and-a-half times the salary for working overtime.

Given below are the staff salaries.

Resource

Hourly Rate (€)

Notes

Project manager

50


Lead engineer

45


Design engineer

40


Software engineer

40


Hardware engineer

40


Manufacturing staff

150

The manufacturing staff consists of six people.

Installation staff

75

The installation staff consists of three technicians.

The project plan is as follows:

Task #

Description

Duration (days)

Start

Finish

Predecessor

1

Acceptance of the contract

0

1/4

1/4


2

HPI engineering site survey

3

1/4

1/6

1

3

Hardware design

14

1/7

1/26

2

4

Human-Machine Interface (HMI) software design

20

1/27

2/23

3

5

HMI software development

25

3/24

4/29

11

6

Software integration and testing

10

4/30

5/14

5

7

Unit 1 hardware testing

3

2/10

2/12

17

8

System testing

5

5/17

5/21

6,7,3

9

HPI factory acceptance test (FAT)

5

5/24

5/28

8

10

Customer-witnessed FAT

5

6/1

6/7

9

11

Functional design specification

20

2/24

3/23

4

12

HPI review design documentation

2

2/24

2/25

4

13

Customer review functional design

5

2/26

3/4

12

14

Preparation of FAT specifications

2

1/27

1/28

3

15

Creation of the operations and maintenance manual

10

6/8

6/21

10

16

Final documentation

4

7/19

7/22

25

17

Manufacture unit 1

10

1/27

2/9

3

18

Delivery to the site

4

6/22

6/25

15

19

Travel to the site for installation

1

6/25

6/25

18FF

20

Demolition: Control panel

2

6/28

6/29

19

21

Installation: Control panel

8

6/30

7/9

20

22

Installation: Fuel system

2

7/12

7/13

21

23

Travel from the site after installation

1

7/14

7/14

22

24

Travel to the site for commissioning

1

7/14

7/14

23FF

25

Checking of the cold loop

2

7/15

7/16

24

26

Checking of the hot loop

4

7/19

7/22

25

27

Commissioning

3

7/23

7/27

26

28

Training of the client's team in operations

3

7/28

7/30

27

29

Training of the client's team in maintenance procedures

1

8/2

8/2

28

30

Procurement of customer acceptance

0

8/2

8/2

29

31

Travel from the site after commissioning

1

8/3

8/3

30

32

Project closure

2

8/4

8/5

31

33

Project management

150

1/4

8/5

1

The resource usage, by task, is as follows:

Task Name

Resource Names

Acceptance of the contract


HPI engineering site survey

Lead engineer

Project management

Project manager

Hardware design

Design engineer

HMI software design

Design engineer

Preparation of FAT specifications

Lead engineer

Manufacture unit 1

Manufacturing staff

Unit 1 hardware testing

Hardware engineer

Functional design specification

Design engineer

HPI review design documentation

Lead engineer

Customer review functional design


HMI software development

Software engineer

Software integration and testing

Software engineer

System testing

Lead engineer

HPI factory acceptance test (FAT)

Lead engineer

Customer-witnessed FAT


Creation of the operations and maintenance manual

Design engineer

Delivery to the site


Travel to the site for installation

Installation staff

Demolition: Control panel

Installation staff

Installation: Control panel

Installation staff

Installation: Fuel system

Installation staff

Travel from the site after installation

Installation staff

Travel to the site for commissioning

Lead engineer

Checking of the cold loop

Lead engineer

Final documentation

Design engineer

Checking of the hot loop

Lead engineer

Commissioning

Lead engineer

Training of the client's team in operations

Lead engineer

Training of the client's team in maintenance procedures

Lead engineer

Procurement of customer acceptance


Travel from the site after commissioning

Lead engineer

Project closure

Lead engineer, design engineer, software engineer

Your company observes UK holidays. For 2010, these holidays are:

January 1

New Year's Day

April 2

Good Friday

April 5

Easter Monday

May 3

Early May Bank Holiday

May 31

Spring Bank Holiday

August 30

Summer Bank Holiday

December 27

Christmas Day

December 28

Boxing Day

If the project starts on January 4, it will finish on August 5. The contract with Huston Power, Inc. includes penalties if the project completes later than August 5. As of February 26, the following tasks have been completed:

Task Name

Start

Finish

Duration (days)

Acceptance of the contract

1/4

1/4

0

HPI engineering site survey

1/4

1/6

3

Hardware DESIGN

1/7

1/27

15

HMI software design

1/28

2/26

22

Unit 1 hardware testing

2/11

2/17

5

Preparation of FAT specifications

1/28

2/1

3

Manufacture unit 1

1/28

2/10

10

Using the data provided, calculate the following:

The original cost estimate

The new cost estimate as of February 26

Changes that can be made to the schedule to complete the project by August 5

The planned value (PV) as of February 26

The actual cost (AC) as of February 26

The earned value (EV) as of February 26

The value of the following as of February 26:

Cost variance (CV)

Cost performance index (CPI)

Schedule variance (SV)

Schedule performance index (SPI)

Estimate to complete (ETC)

Estimate at completion (EAC)

Business Management, Management Studies

  • Category:- Business Management
  • Reference No.:- M9809295

Have any Question?


Related Questions in Business Management

Name a company that addressed a recent ethical problem in a

Name a company that addressed a recent ethical problem in a positive way. Also, explain how or if this positively affects us as a community?

When it is appropriate to use the trade-off process what

When it is appropriate to use the trade-off process. What conditions apply, and the technical evaluation criteria that might be used?

Need help with a essay with the following phrase for

Need help with a essay with the following phrase for analyzing : " Capitalism is at the heart of how people and organisations are managed in contemporary society" May i ask for a better explanation of the question? Also ...

How could these three tenets of the auburn creed be used to

How could these three tenets of the Auburn Creed be used to motivate others: "I believe that this is a practical word and that I can count only on what I earn. Therefore, I believe in work, hard work." "I believe in educ ...

How can these two tenets of the auburn creed by used in

How can these two tenets of the Auburn Creed by used in addressing teamwork issues: "I believe in honesty and truthfulness, without which I cannot win the respect and confidence of my fellow men." "I believe in the human ...

Discuss the advantages of having and interacting in a

Discuss the advantages of having and interacting in a diverse workplace. Consider the wide range of ideas and perspectives that a range of team members bring to a team, that are of differing ages, ethnic backgrounds and ...

Parmigiano-reggiano global recognition of geographical

Parmigiano-Reggiano: Global Recognition of Geographical Indications What historical factors have helped support the consortium's claims for the geographic specificity of Parmigiano-Reggiano and Parmesan? What are the eco ...

Communication planthis communication plan will be a roadmap

Communication Plan This communication plan will be a roadmap on how the new division will best be able to communicate with Biotech's corporate headquarters, suppliers, other divisions, and internally. This should lay out ...

Discuss strategies to obtain feedback from a customer and

Discuss strategies to obtain feedback from a customer and clients when working in sales.

Describe different networking methods and the advantages

Describe different networking methods and the advantages and disadvantages of them?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As