Marcy is managing a project for her company. Her project's budget is $250,000. She has find outd the cost performance index (CPI) to be .91 and her costs are $175,000. What is Marcy's estimate at completion (EAC)?

A. $115,750
B. $275,000
C. $265,000
D. $250,000

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M977734

Have any Question?


Related Questions in Operation Management

1 what you understand from motivation and contingency

1. What you understand from Motivation and Contingency Theories with proper explanation and with proper reference. 2. Give some examples on how one's philosophy or beliefs about leadership fit with the competing values m ...

Hold-up problemassume that an indian firm is contacted by a

Hold-up problem Assume that an Indian firm is contacted by a multinational car company to produce brake systems. This requires an initial specific investment of I from the Indian sub- contractor and a variable cost c per ...

1 how has technology issues impacted uber2 what strategies

1. How has technology issues impacted Uber? 2. What strategies could have prevented these problems? 3. Do you feel technology businesses have an advantage or disadvantage over non-technology businesses? Explain? 4. What ...

The first four units examine traditional leadership

The first four units examine traditional leadership, adaptive leadership and followership concepts and applications. While these concepts may appear to be disjointed, they can be woven together for an effective leadershi ...

1 in 300 words summarize the corona v corporation of the

1. In 300 words summarize the Corona v. Corporation of the City of Mississauga case. (with a conclusion at the end) 2. Build a case for adaptive leadership being more of a situational theory than a leader centered or fol ...

1 how has the systems approach influenced current

1. How has the systems approach influenced current management techniques? 2. What is the significant key variable that emphasized in the human relations approach of management theory? 3. Which theory applies most to the ...

Shanghai general motors the rise of a late-comerwhat are

Shanghai General Motors: The Rise of a Late-comer What are the success factors that contribute to the joint venture’s (SGM’s) rapid growth? What are the threats and opportunities faced by SGM, in the competitive automobi ...

Prompt specialist are those who work in the field of

Prompt: Specialist are those who work in the field of policing but with a specific knowledge base in a certain area or "specialty". They can work anything from human trafficking cases to cyber crime. Often, due to one's ...

Research analysis for businesspurpose of assignmentthe

Research Analysis for Business Purpose of Assignment The purpose of this assignment is the creation of a research analysis. Every day, consumers make millions of decisions that impact the marketplace and influence firms' ...

1 list and explain the six most notable urban transport

1. List and explain the six most notable urban transport problems. Which of them constitutes the most prevalent in American Society? 2. Explain in 5-7 sentences the importance of positive communication skills in the work ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As