Greendale Stadium Case

The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction must start July 1, 2011, and be completed in time for the start of the ?014 season. A penalty clause of S100,000 per day of delay beyond May 20, 2014, is written into the contract.

Ben Keith, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as S2 million on the project. He also said if hey are successful, the prospects for future projects are quite good since there is a projected renaissance in building classic ball parks with modem luxury boxes.

ASSIGNMENT

Given the information provided in Table 6.3, construct a network schedule for the stadium project and answer the following questions:

1. Will the project be able to be completed by the May 20 deadline? How long will it take?

2. What is the critical path for the project?

3. Based on the schedule would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule.

TABLE 6.3

Greendale Stadium Case

 

 

ID

Activity

Duration

Predecessor(s)

1

Baseball Stadium

 

 

2

Clear stadium site

70 days

-

3

Demolish building

30 days

2

4

Set up construction site

70 days

3

5

Drive support piling

120 days

2

6

Pour lower concrete bowl

120 days

5

7

Pour main concourse

120 days

3,6

8

Install playing field

90 days

3,6

9

Construct upper steel bowl

120 days

3,6

10

Install seats

140 days

7,9

11

Build luxury boxes

90 days

7,9

12

Install jumbotron

30 days

7,9

13

Stadium infrastructure

120 days

7,9

14

Construct steel canopy

75 days

10

15

Light installation

30 days

14

16

Build roof supports

90 days

6

17

Construct roof

180 days

16

18

Install roof tracks

90 days

16

19

Install roof

90 days

17,18

20

Inspection

20 days

8,11,13,15,19

The work on the stadium begins by driving 160 support pilings, which will take 120 days. Next comes the pouring of the lower concrete bowl (120 days). Once this is done and the construction site has been set up, then the pouring of the main concourse (120 days), the installation of the playing field (90 days), and the construction of the upper steel bowl can occur (120 days).

Once the concourse and upper bowl are completed, work can start simultaneously on building the luxury boxes (90 days), installing the seats (140 days), installing the jumbotron (30 days), and installing stadium infrastructure (120 days) which includes: bathrooms, lockers, restaurants, etc. Once the seats are installed then the steel canopy can be constructed (75 days) followed by the installation of the lights (30 days).

The retractable roof represents the most significant technical challenge to the project. Building the roof track supports (90 days) can begin after the lower concrete bowl is constructed.

At this time the dimensions of the roof can be finalized and the construction of the roof at a separate site can begin (180 days). After the roof supports are completed then the roof tracks can be installed (90 days). Once the tracks and the roof are completed then the roof can be installed and made operational (90 days). Once all activities are completed it will take 20 days to inspect the stadium.

For purposes of this case assume the following:

1. The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.

2. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.

3. The construction crew work Monday through Friday.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92712375
  • Price:- $20

Priced at Now at $20, Verified Solution

Have any Question?


Related Questions in Operation Management

Assignmentwrite a 2 page analysis of physician quality

Assignment Write a 2 page analysis of physician quality practice data. Recommend three strategies for improving physician quality practice rankings on physician profiling and quality report cards. Justify your recommenda ...

Company wal-mart or starbuck choose one company and write

Company: Wal-Mart or StarBuck (Choose one Company and write on the following guidline) 1. Define the process: its start, end, and what it does. 2. Describe the process: list the key tasks performed and sequence of steps, ...

1 discuss why marketing strategies should reflect the

1. Discuss why marketing strategies should reflect the healthcare organization's desired position in the marketplace. Discuss why branding as a strategic approach is necessary for hospitals and healthcare organizations t ...

Ask any supply chain manager and shell tell you that one of

Ask any supply chain manager, and she'll tell you that one of the biggest debates in her field today is whether or not to outsource the supply chain to foreign countries where parts can be manufactured more cheaply. Visi ...

1 discuss the significance of the numerator and denominator

1. Discuss the significance of the numerator and denominator in the corporate value proposition. Who benefits from the maximization of corporate valuation? (Note: Milton Friedman, among other notable financial economists ...

Read the following scenarioyou are the ceo of bonner a

Read the following scenario: You are the CEO of Bonner, a U.S.-based farm equipment corporation. Bonner recently announced the release of an innovative new tractor with technology based on a patented invention developed ...

Imperial jewelers manufactures and sells a gold bracelet

Imperial Jewelers manufactures and sells a gold bracelet for $406.00. The company’s accounting system says that the unit product cost for this bracelet is $259.00 as shown below: Direct Materials: $143 Direct Labor: 85 M ...

1 ho do you determine which process improvement tools

1. Ho do you determine which process improvement tools should be used to ensure quality if care in healthcare organisations? What is the cost and return of each approach? 2. Mike Mechanic repaired Alice Ace’s automobile ...

Your chemical facility consumes significant amounts of

Your chemical facility consumes significant amounts of water. Six samples of 15 observations have been taken with the results shown here: Sample Mean Range 1 478,550 1,222 2 491,008 1,442 3 471,119 958 4 486,533 1,173 5 ...

1 explain the concepts of differentiation and integration

1. Explain the concepts of differentiation and integration. In what type of environmental uncertainty will differentiation and integration be greatest and least? Illustrate with examples. 2. How does the desire for legit ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As