Garden Variety Flower Shop uses 750 clay pots a month. The pots are purchased at $2 each. Annual carrying cost per pot are estimated to be 30 percent of the cost and ordering costs are $20 per order. The manager has been using an order size of 1500 flower pots.
If order-lead time is one week (ie 0.25 month) what is the re-order point?