From the Eagles to the Magic: Converting the Amway Center

The massive 875,000-square-foot Amway Center in Orlando, Florida, is a state-of-the-art sports entertainment center. While it is the home of the Orlando Magic basketball team, it is a flexible venue designed to accommodate a vast array of entertainment. The facility is used for everything from a concert by the Eagles or Britney Spears, to ice hockey, to arena football, to conventions, as well as 41 regular season home games played by its major tenant, the National Basketball Association's Orlando Magic. The building is a LEED-certified (Leadership in Energy and Environmental Design), sustainable, environmentally friendly design, with unmatched technology. Dispersed throughout the building are over 1,000 digital monitors, the latest in broadcasting technology, and the tallest high-definition video board in an NBA venue. To fully utilize this nearly $500 million complex, conversions from one event to the next must be done rapidly-often in a matter of hours. Letting the facility sit idle because of delays in conversion is not an option. Well-executed conversions help maximize facility revenue and at the same time minimize expenses. Fast and efficient conversions are critical. Like any other process, a conversion can be analyzed and separated into its component activities, each requiring its own human and capital resources. The operations manager must determine when to do the conversion, how to train and schedule the crew, which tools and capital equipment are necessary, and the specific steps necessary to break down the current event and set up for the next. In addition to trying to maintain a stable crew (typically provided by local staffing companies) and to maintain control during the frenzied pace of a conversion, managers divide the workforce into cross-trained crews, with each crew operating in its own uniquely colored shirt.

At the Amway Center, Charlie Leone makes it happen. Charlie is the operations manager, and as such, he knows that any conversion is loaded with complications and risks. Concerts add a special risk because each concert has its own idiosyncrasies-and the breakdown for the Eagles concert will be unique. Charlie and his crews must anticipate and eliminate any potential problems. Charlie's immediate issue is making a schedule for converting the Eagles' concert venue to an NBA basketball venue. The activities and the time for various tasks have been determined and are shown in Table 15.3.

Table 15.3 - Concert-to-Basketball Conversion Tasks

Available crew size= 16, including two fork truck drivers

TIME ALLOWED

TASKS

CREW AND TIME REQUIRED

3 to 4 hr

11:20 PM Performance crew begins teardown of concert stage&equipment

Concert's Responsibility

45 min

11:20 PM Clear Floor Crew

 


Get chair carts from storage

10 for 15 min


Clear all chairs on floor, loading carts starting at south end, working north

16 for 30 min


Move chair carts to north storage and stack as they become full

(includes 1 fork truck operator)

15 min

11:50 PM (Or as soon as area under rigging is cleared)

6 for 15 min


Set up retractable basketball seating on north end



Take down railing above concert stage



Place railings on cart and move to storage


2.5 hr

12:05 AM Basketball Floor Crew

8


Position 15 basketball floor carts on floor



Mark out arena floor for proper placement of basketball floor



Position basketball floor by section



Assemble/join flooring/lay carpets over concrete



Position basketball nets in place



Set up scorer tables



Install risers for all courtside seating



Install 8-ft tables on east side of court


2.5 hr

Seating Unit Crew Starts same time as basketball Floor Crew

8


Set up retractable basketball seating on north end

(includes 2 fork truck operators)


Set up retractable basketball seating on south end



(Can only be done after concert stage and equipment is out of way)



Install stairs to Superstar Seating


2 hr

Board Crew Starts after seating unit crew finishes

4


Install dasher board on south end



Move stairs to storage


2 hr

Chair Crew Starts after seating unit crew finishes

12


Get chair carts from storage



Position chair carts on floor



Position chairs behind goals, courtside, and scorer tables



Clean, sweep, and place carts in order


45 min

End-of-Shift Activities Starts after chair crew finishes

12


Perform check list items



Ensure that steps and stairways and railings are in place and tight



Check all seats are in upright position and locked in place



Report any damaged seats or armrests in need of repair



Verify exact number of chairs behind goals, courtside, and scorer tables


15 min

Check out Starts after end-of-shift activities

16


Check for next conversion date and time and inform crew. Starts after end of shift activates



Report any injuries



Punch out all employees before leaving



8:00 AM Floor ready for Magic practice


Discussion Questions:

1. Make a Gantt chart to help Charlie organize his crew to perform the concert-to-basketball conversion. Note: Do not include the teardown of the concert stage and equipment, as that is the responsibility of the concert crew.

2. What time will the floor be ready?

3. Does Charlie have any extra personnel or a shortage of personnel? If so how many?

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92173053
  • Price:- $20

Priced at Now at $20, Verified Solution

Have any Question?


Related Questions in Operation Management

The existence of a parallel private healthcare system

The existence of a parallel private healthcare system within a broader public Beveridge system provides an opportunity for patients who are unhappy with the service they receive in the public system. Since higher income ...

1 think about a healthcare organizationclinic create a

1. Think about a healthcare organization/clinic. Create a discipline and termination procedure and then analyze what is missing and how you would modify the procedure to make it more effective. 2. Which type of written c ...

Topics 1 getting hired amp advancing in onersquos

Topics: 1. Getting Hired & Advancing in One’s Discipline             2. Legal Rights & Ethical Responsibilities Instruction: Choose something that YOU would like to discuss associated with these two subjects.

1 in a small struggling technology company the employees

1. In a small struggling technology company, the employees are aware that processes and structures must change if the company is going to survive, but the leadership is not. What is likely to occur with regard to the jou ...

1 what are the three types of pricing strategies services

1. What are the three types of pricing strategies services that services employ? Using a real life example (Six Flags, The Brewers, etc.) illustrate each strategy. 2. Identify 3 types of non-store retailing and discuss a ...

Purpose of assignment this assignment provides students

Purpose of Assignment: This assignment provides students with the business scenario. The scenario requires students to imagine themselves inside an organization as consultants and to determine how to respond given the or ...

As my generation baby boomers leave the workforce over the

As my generation (baby boomers) leave the workforce over the next couple of decades, will the remaining employees be equipped to maintain the level of knowledge necessary to run American business? This is actually a simp ...

Discuss case 152 food and drug administration v brown amp

Discuss Case 15.2 Food and Drug Administration v. Brown & Williamson Tobacco Corporation with your Learning Team. This case is found in The Legal and Regulatory Environment of Business, pg. 459. Develop a 350- to 700-wor ...

1- how does the mission statement relate to the

1- How does the mission statement relate to the organizational structure and culture of a firm? 2- How is the external environment analyzed, i.e., what are the macro environmental forces? 3- What is organizing? What is i ...

1 a new full-service attendant-staffed fuel and car service

1. A new full-service, attendant-staffed fuel and car service station on Interstate 95 will service only northbound cars. The manager estimates that customers will arrive every 4 minutes and will require 6 minutes to be ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As