Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The prject is scheduled to begin May 1, and a September 1 (17- week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times:
Activity Immediate Predecessor Time
A - 3
B - 1
C - 2
D A,B,C 4
E C,D 5
F A 3
G D,F 6
H E 4
A) Draw a project network
B) What are the critical values
C) What activity has the most slack time
D) Will the prokect be completed by September 1?