Ask Question, Ask an Expert

+1-415-315-9853

info@mywordsolution.com

Ask Operation Management Expert

problem 1:

Earned Value Management is the systematic approach to measurement and integration of cost, schedule, and technical accomplishments in a project. List all the benefits which are associated with this technique.

problem 2:

PK Motors Ltd embarked on the pilot project to manufacture 2000 units of a new model vehicle. The total cost of manufacture is estimated at $27m and the project must be completed in 30 weeks. The rate of project progress is anticipated to be uniform and linear. At the end of week 18, the actual cost of work performed (ACWP) amounted to $17.1m and the number of cars produced was 600 units. As a project manager, you’re requested to report the project status. Your answer must point on the following:

i) A graphical presentation of the project status

ii) Cost Variance (CV)

iii) Schedule Variance (SV)

iv) Cost Performance Index (CPI)

v) Schedule Performance Index (SPI)

vi) Estimate To Complete (ETC)

vii) Estimate At Completion (EAC)

viii) Estimated time to complete

Consider the results of Earned Value Analysis and briefly state whether the project is ahead or behind schedule and whether it is under or over budget.

problem 3:

Projects are extensively known for their tendency to run late and over-budget.

(i) Select an organization of your choice and in brief illustrate out the main risks to which development projects are exposed.

(ii) Discuss and illustrate out the techniques which are available for coping with those risks.

problem 4:

Almost all projects suffer change to their current “definition” at some point in their evolution. Changes might be proposed by any of stakeholders associated with the project. Change might be unavoidable or highly desirable; it might equally be unnecessary and not useful. It is indispensable that any proposed change to the project be formally controlled. Illustrate out how project controls relative to alters are managed.

problem 5:

Projects generate and absorb important quantities of information. Discuss and illustrate out the significance of an effective information management system.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M98416

Have any Question? 


Related Questions in Operation Management

Adrian reese a resident of new york owned a strip mall

Adrian Reese, a resident of New York, owned a strip mall located in Ohio, which he leased out to different businesses. The tenants in the building had complained that the two public restrooms were substandard and in need ...

Pareto chart practice assume you are working on a project

Pareto Chart Practice Assume you are working on a project to improve customer service. Create a Pareto chart based on the information on the following table. Use the Pareto chart template so that your resulting chart loo ...

Fantastic styling salon is run by three stylists jenny

Fantastic Styling Salon is run by three? stylists, Jenny? Perez, Jill? Sloan, and Jerry? Tiller, each capable of serving five customers per? hour, on average. Use POM for Windows or OM Explorer to answer the following qu ...

The design of your jobthink of a specific job current or

The Design of Your Job Think of a specific job (current or previous) you have held and name it. Please answer the following questions about those work activities. Respond to each item below, indicating whether it is Most ...

1 what is the penalty for violating the paternity leave

1. What is the penalty for violating the Paternity Leave Act? 2. What is Parental Leave and who may avail thereof? 3. Should salary-related benefits (i.e. cash equivalent of unused vacation and sick leave credits, overti ...

How is information about jacksons labor market important in

How is information about Jackson's labor market important in considering whether or not Plump n' Stuffy is in compliance with the Civil Rights Act of 1964? Discuss the relevant data you have found associated with Jackson ...

For singapore corporate tax the investment allowance

For Singapore Corporate tax, the Investment allowance granted in the scenario below, would it be based on the qualifying expenditure capped of $5,000,000 or the approved fixed capital expenditure? In addition, would PIC ...

Prior to the first meeting of the rww enterprise policy

Prior to the first meeting of the RWW Enterprise Policy Review Committee, Mike asked Iris to meet him in his office. "You've convinced me that IT and InfoSec policy are tightly integrated," Mike said, motioning for Iris ...

What are the components of and steps in the collective

What are the components of and steps in the collective bargaining process? Evaluate them.

What is the depreciation deduction for a new specialized

What is the depreciation deduction for a new specialized equipment (7-year property) costing $1,600,000. The corporation elected Section 179 expensing for this equipment but elected not to claim any bonus depreciation.

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

WalMart Identification of theory and critical discussion

Drawing on the prescribed text and/or relevant academic literature, produce a paper which discusses the nature of group

Section onea in an atwood machine suppose two objects of

SECTION ONE (a) In an Atwood Machine, suppose two objects of unequal mass are hung vertically over a frictionless

Part 1you work in hr for a company that operates a factory

Part 1: You work in HR for a company that operates a factory manufacturing fiberglass. There are several hundred empl

Details on advanced accounting paperthis paper is intended

DETAILS ON ADVANCED ACCOUNTING PAPER This paper is intended for students to apply the theoretical knowledge around ac

Create a provider database and related reports and queries

Create a provider database and related reports and queries to capture contact information for potential PC component pro