Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Homework Help/Study Tips Expert

Earned Value Exercise

Complete the following problems:

1. The following project is at the end of its first week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.

Task

Predecessors

Duration in days

Planned Value ($)

Actual Cost ($)

Percent Complete

A

None

2

550

700

100

B

None

3

950

1450

100

C

A

2

300

350

50

D

A

5

700

650

20

E

B ,C

6

1000

350

10

To do this exercise, it is best to start with a Gantt chart depicting the task relationships.

CV ______________________

CPI ________________

SV ______________________

SPI ________________

EAC _____________________

2. Using the following information below, calculate the cost performance index and the schedule performance index. Then calculate the estimate at completion
Planned value: 7700
Earned value: 7100
Actual costs: 7900
Budget at completion: 39900

CPI _______________________

SPI _____________________________

EAC ______________________

3. The following project is at the end of its third week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.

Task

Predecessors

Duration in days

Planned Value ($)

Actual Cost ($)

Percent Complete

A

None

3

700

750

100

B

A

5

1100

1400

100

C

A

2

250

300

100

D

A

5

900

600

100

E

B ,C

6

1300

1200

100

F

C

10

11000

12500

75

G

F

7

900

0

0

H

G

8

1500

0

0

To do this exercise, it is best to start with a Gantt chart depicting the task relationships.

CV ______________________

CPI ________________

SV ______________________

SPI ________________

EAC _____________________

4. Mary is the project manager for a web design project for Newberry Pet Foods. So far in the six weeks (of the twelve week project), Mary's team has completed five tasks which had a combined planned value of $8800. However, the team spent $9200 to complete those tasks. She has five additional tasks to complete the project. What are the PV, EV, AC, CV, SV, CPI, and SPI for Mary's project?

5. Consider the following information:

PV=6700

EV=5200

AC=7400

BAC=32000

Expected Duration=12 weeks

Calculate the following:

CV __________________

SV __________________

CPI __________________

SPI __________________

EAC __________________

Duration at Completion _______________

Homework Help/Study Tips, Others

  • Category:- Homework Help/Study Tips
  • Reference No.:- M91648080
  • Price:- $25

Guranteed 24 Hours Delivery, In Price:- $25

Have any Question?


Related Questions in Homework Help/Study Tips

Question please answer each question in 75 words a piece

Question: Please answer EACH question in 75 words A PIECE. Use references, if needed. 1. Write down at least one specific aspect regarding Professional, Ethical, and Social Responsibility that you need to still develop a ...

Assessment task descriptionmedia content can strongly

ASSESSMENT TASK: DESCRIPTION Media content can strongly influence an audience's thoughts, beliefs and attitudes. Several studies have indicated that negative media portrayals regarding culturally diverse and disadvantage ...

Assignment reflective practitioner journal response

Assignment : Reflective Practitioner Journal Response -Assessing Oral Language and Vocabulary In this assignment, you will write the third reflective journal response of this course. You will write six such journal respo ...

Question advanced practice nurses should be able to

Question: Advanced practice nurses should be able to critique, evaluate, and use theory. They should be able to integrate and apply a wide range of theories from nursing and other sciences into a comprehensive and holist ...

Assignment detailswhat is a revocation hearingexplain the

Assignment Details What is a revocation hearing? Explain the steps involved in a revocation hearing and what rights the offender has.

Target audience exerciseduring super bowl lii there were

Target Audience Exercise During Super Bowl LII, there were many people who were watching the television in anticipation of the commercials. Corporations spent millions of dollars on these commercials (which lasted less t ...

Assignment - reportplease choose landcare australia

Assignment - Report Please choose "Landcare Australia" organisation for this case study. Prepare a report that is a case study of a particular industry, agency or organisation's process of engaging Indigenous people in n ...

Assignment health policy and law basicsas a chief

Assignment : Health Policy and Law Basics As a chief operating officer of a hospital, you have been tasked with opening a new ambulatory care center in your city. Write a 2-3 page paper in which you: Specify whether you ...

Respond to two students 300 words each add to the

Respond to two students 300+ words each, add to the conversation not critique their work. Citations in MLA format. First response Virgil's poem The Aeneid begins with "Wars and a man I sing- an exile driven on by fate". ...

Question write a 500-700 word position argument on one of

Question: Write a 500-700 word position argument on one of the following topics: • Should college education be free to American citizens (a bachelor's degree) • Should large places of employment (1,000 employees or more) ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As