Earned Value Exercise

Complete the following problems:

1. The following project is at the end of its first week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.

Task

Predecessors

Duration in days

Planned Value ($)

Actual Cost ($)

Percent Complete

A

None

2

550

700

100

B

None

3

950

1450

100

C

A

2

300

350

50

D

A

5

700

650

20

E

B ,C

6

1000

350

10

To do this exercise, it is best to start with a Gantt chart depicting the task relationships.

CV ______________________

CPI ________________

SV ______________________

SPI ________________

EAC _____________________

2. Using the following information below, calculate the cost performance index and the schedule performance index. Then calculate the estimate at completion
Planned value: 7700
Earned value: 7100
Actual costs: 7900
Budget at completion: 39900

CPI _______________________

SPI _____________________________

EAC ______________________

3. The following project is at the end of its third week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.

Task

Predecessors

Duration in days

Planned Value ($)

Actual Cost ($)

Percent Complete

A

None

3

700

750

100

B

A

5

1100

1400

100

C

A

2

250

300

100

D

A

5

900

600

100

E

B ,C

6

1300

1200

100

F

C

10

11000

12500

75

G

F

7

900

0

0

H

G

8

1500

0

0

To do this exercise, it is best to start with a Gantt chart depicting the task relationships.

CV ______________________

CPI ________________

SV ______________________

SPI ________________

EAC _____________________

4. Mary is the project manager for a web design project for Newberry Pet Foods. So far in the six weeks (of the twelve week project), Mary's team has completed five tasks which had a combined planned value of $8800. However, the team spent $9200 to complete those tasks. She has five additional tasks to complete the project. What are the PV, EV, AC, CV, SV, CPI, and SPI for Mary's project?

5. Consider the following information:

PV=6700

EV=5200

AC=7400

BAC=32000

Expected Duration=12 weeks

Calculate the following:

CV __________________

SV __________________

CPI __________________

SPI __________________

EAC __________________

Duration at Completion _______________

Homework Help/Study Tips, Others

  • Category:- Homework Help/Study Tips
  • Reference No.:- M91648080
  • Price:- $25

Guranteed 24 Hours Delivery, In Price:- $25

Have any Question?


Related Questions in Homework Help/Study Tips

Review the website airmail service from the smithsonian

Review the website Airmail Service from the Smithsonian National Postal Museum that is dedicated to the history of the U.S. Air Mail Service. Go to the Airmail in America link and explore the additional tabs along the le ...

Read the article frank whittle and the race for the jet

Read the article Frank Whittle and the Race for the Jet from "Historynet" describing the historical influences of Sir Frank Whittle and his early work contributions to jet engine technologies. Prepare a presentation high ...

Overviewnow that we have had an introduction to the context

Overview Now that we have had an introduction to the context of Jesus' life and an overview of the Biblical gospels, we are now ready to take a look at the earliest gospel written about Jesus - the Gospel of Mark. In thi ...

Fitness projectstudents will design and implement a six

Fitness Project Students will design and implement a six week long fitness program for a family member, friend or co-worker. The fitness program will be based on concepts discussed in class. Students will provide justifi ...

Read grand canyon collision - the greatest commercial air

Read Grand Canyon Collision - The greatest commercial air tragedy of its day! from doney, which details the circumstances surrounding one of the most prolific aircraft accidents of all time-the June 1956 mid-air collisio ...

Qestion anti-trustprior to completing the assignment

Question: Anti-Trust Prior to completing the assignment, review Chapter 4 of your course text. You are a manager with 5 years of experience and need to write a report for senior management on how your firm can avoid the ...

Question how has the patient and affordable care act of

Question: How has the Patient and Affordable Care Act of 2010 (the "Health Care Reform Act") reshaped financial arrangements between hospitals, physicians, and other providers with Medicare making a single payment for al ...

Plate tectonicsthe learning objectives for chapter 2 and

Plate Tectonics The Learning Objectives for Chapter 2 and this web quest is to learn about and become familiar with: Plate Boundary Types Plate Boundary Interactions Plate Tectonic Map of the World Past Plate Movement an ...

Question critical case for billing amp codingcomplete the

Question: Critical Case for Billing & Coding Complete the Critical Case for Billing & Coding simulation within the LearnScape platform. You will need to create a single Microsoft Word file and save it to your computer. A ...

Review the cba provided in the resources section between

Review the CBA provided in the resources section between the Trustees of Columbia University and Local 2110 International Union of Technical, Office, and Professional Workers. Describe how this is similar to a "contract" ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As