Q 1. Developing Risk Mitigation Strategies. Develop a preliminary risk mitigation strategy for each of risk factors identified in Problem 2. If you were to prioritize your efforts which risk factors would you address first? Why?
2. Quantitative Risk Assessment. Assume subsequent information:
Probability of Failure Consequences of Failure
Maturity = .3 Cost = .1
Complexity = .3 Schedule = .7
Dependency = .5 Performance = .5
factor for this project. Would you assess this level of risk as low, moderate or high? Why?