stephen hall is developing a program in supply chain management certification for managers. hall has listed a number of activities that must be completed before a training program of this nature could be conducted. the activities, immediate predecessors, and times appear in the accompanying table .
activity immediate predecessor time (days)
A 2
B 5
C 1
D B 10
E A,D 3
F C 6
G E,F 8
A) develop an AON network for this problem
B) what is the critical path ?
C) what is the total project completion time?
D) what is the slack time for each individual activity?