Step-by-step answer to Linear Programming Model

The Eastside Manufacturing Company produces four different aircraft components from fabricated sheet metal for several major aircraft companies. The manufacturing process consists of four operations - stamping, assembly, finishing, and packaging. The processing time per unit for each of the operations and total available hours per year to produce these components are given below.

Operation Component (hr/unit)
1 2 3 4 Total Hours per Year
Stamping 0.06 0.17 0.10 0.14 700
Assembly 0.18 0.20 -- 0.14 700
Finishing 0.07 0.20 0.08 0.12 800
Packaging 0.09 0.12 0.07 0.15 600
The sheet metal required for each component, the estimated annual demand, and the profit contribution provided by each component, are as follows:

Component Sheet Metal
(ft2) Estimated Annual Demand Profit Contribution
$
1 2.6 2,600 90
2 1.4 1,800 100
3 2.5 4,100 80
4 3.2 1,200 120

The company has 15,000 square feet of fabricated metal delivered each month. The company has the following prioritized production goals for these components:

? Avoid the use of overtime given the low profit margins.
? Meet all component demand.
? Achieve an annual profit contribution of at least $700,000
? Avoid additional material orders - pricing is dependent upon annual contracts with fixed amounts and delivery schedules

a. Formulate a linear programming model to determine the quantity of each component to produce to achieve the company's goals.

Answer:The decision variables are: x1 the quantity of the component 1 produced and sold
x2 the quantity of the component 2 produced and sold
x3 the quantity of the component 3 produced and sold
x4 the quantity of the component 4 produced and sold
First we prepare the entire program as a linear program
The objective function without any goal achievement requirement is maximization of profit
The profit as an objective function is 90x1 + 100x2 + 80x3 + 120x4 Eq(1)
The operation time availability constraints for each operation is as given below
0.06x1 + 0.17x2 + 0.10x3 + 0.14x4 <= 700 Eq(2) Stamping operation
0.18x1 + 0.20x2 + 0.14x4 <= 700 Eq(3) Assembly operation
0.07x1 + 0.20x2 + 0.08x3 + 0.12x4 <= 800 Eq(4) Finishing operation
0.09x1 + 0.12x2 + 0.07x3 + 0.15x4 <= 600 Eq(5) Packaging operation
The sheet metal availability constraint is
2.6x1 + 1.4x2 + 2.5x3 + 3.2x4 <= 15000 Eq(6) Sheet metal availability
Annual demand requirement is
x1 >= 2600 Eq(7) Component 1
x2 >= 1800 Eq(8) Component 2
x3 >= 4100 Eq(9) Component 3
x4 >= 1200 Eq(10) Component 4
Now we prepare goal program considering each of the goals in the order of the priority. Each goal is given priority order based on importance.
P1: Avoid the use of overtime given the low profit margins
Let us define the deviation variables for this goal. There are four constraints for operations hours, one each for each department. Let us say d1+ and d1- be the deviation variables for the amount by which the total operations hours exceeds and is less than the target value of 700 for stamping operation. Similarly the deviation variables for other constraints for operations time are written
The goal equation for stamping operation is
0.06x1 + 0.17x2 + 0.10x3 + 0.14x4 - d1+ + d1- = 700
The goal equation for assembly operation is
0.18x1 + 0.20x2 + 0.14x4 - d2+ + d2- = 700
The goal equation for finishing operation is
0.07x1 + 0.20x2 + 0.08x3 + 0.12x4 - d3+ + d3- = 800
The goal equation for packaging operation is

0.09x1 + 0.12x2 + 0.07x3 + 0.15x4 - d4+ + d4- = 600
Next flexible constraint is raw material availability, as we have to avoid additional orders. Let us say d5+ and d5- be the deviation variables when raw material required exceeds or less than the target value of 15000. The goal equation for this constraint is
2.6x1 + 1.4x2 + 2.5x3 + 3.2x4 - d5+ + d5- = 15000
Note that we have to avoid overtime and hence all the exceed deviation variables needs to be minimized. The linear program P1 at priority level 1 is
Minimize: d1+ + d2+ + d3+ + d4+
Subject to
x1 >= 2600
x2 >= 1800
x3 >= 4100
x4 >= 1200

90x1 + 100x2 + 80x3 + 120x4 >= 700000

2.6x1 + 1.4x2 + 2.5x3 + 3.2x4 - d5+ + d5- = 15000
All the variables including the deviation variables and decision variables are non-negative
We solve the above linear program and obtain optimal solution. The values of the deviation variables in the objective function are noted down. In the next level program the values of the deviation variables in the above are included as hard constraints.
P2: Avoid additional material orders
The objective is to minimize the over usage of the materials and hence we have
Minimize: d5+

Subject to
x1 >= 2600
x2 >= 1800
x3 >= 4100
x4 >= 1200

90x1 + 100x2 + 80x3 + 120x4 >= 700000
d1+ = optimal value in P1
d2+ = optimal value in P1
d3+ = optimal value in P1
d4+ = optimal value in P1
The non-negativity condition.

b. Determine the solution that will best achieve the company's goals in component production, including the quantity of each component produced, the annual profit contribution attained, and the levels of goal achievement.

Answer: Copy-paste the P1 in any solver package and obtain value of deviation variables as mentioned above. Include the optimal values of the deviation variables in P1 as hard constraints in O2 and again solve. The solution obtained in P2 is optimal considering the goals.

c. Determine how the solution would be affected if the first two goal priorities were reversed.

Answer: In this case P2 becomes P1 without any constraints on d1+, d2+, d3+, and d4+. Solve it and obtain optimal value at d5+. Use this value as constraint in next level problem where d1+, d2+, d3+, and d4+ becomes decision variables.

Operation Research, Management Studies

  • Category:- Operation Research
  • Reference No.:- M924886

Have any Question? 


Related Questions in Operation Research

In every organization inputs of some kind services

In every organization, inputs of some kind (services, information, and/or products) are transformed into outputs (services, information, and/or products) on an ongoing, continuous basis, which are of value to internal or ...

A 75-year-old female is an inpatient in bed 1 of room 10 on

A 75-year-old female is an inpatient in bed #1 of Room 10 on a medical telemetry unit. She has been admitted for pneumonia. She is slightly confused. No family is with her in the hospital at this time. The nurse introduc ...

A critical review on use of operations research for

A critical review on use of Operations Research for Decision Making

Business models and consumer choices please respond to the

"Business Models and Consumer Choices" Please respond to the following: Debate It: Take a position on the following statement: Copyright laws protect rights of creative independent artists against a large corrupt music i ...

Monitoring and evaluationinitial postings must be 250-350

Monitoring and Evaluation Initial postings must be 250-350 words (not including references). Effective health care organizations recognize the importance of monitoring the implementation of a strategy as well as ongoing ...

Read and answer following questions with1-2 pages papermike

"Read and answer following questions with1-2 pages paper." Mike graduated from school a few months ago. He applied to various companies and has decided to take a position as a supervisor at a well-known local restaurant. ...

Consider you need to conduct a business forecastdescribe

Consider you need to conduct a business forecast. Describe your forecast process according to the following steps: - Define the purpose of the forecast o Establish a time horizon - Select a forecasting technique o Gather ...

Short essays no required length1 discuss how occupational

Short essays (no required length) 1. Discuss how occupational safety and health laws and regulations are established, implemented and possibly altered. 2. Compare and contrast this with the establishment of environmental ...

Consider the following scenarioyou have held conversations

Consider the following scenario: You have held conversations with Precision Part's leaders and obtained the following information, which you want to use in the development of a 4-year strategic management plan. PPQ Parts ...

In this discussion forum you will discuss the implications

In this discussion forum, you will discuss the implications of not having a clear and precise scope of the project, and why it needs to be approved by higher management. Also discuss the importance of listing, sequencing ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Section onea in an atwood machine suppose two objects of

SECTION ONE (a) In an Atwood Machine, suppose two objects of unequal mass are hung vertically over a frictionless

Part 1you work in hr for a company that operates a factory

Part 1: You work in HR for a company that operates a factory manufacturing fiberglass. There are several hundred empl

Details on advanced accounting paperthis paper is intended

DETAILS ON ADVANCED ACCOUNTING PAPER This paper is intended for students to apply the theoretical knowledge around ac

Create a provider database and related reports and queries

Create a provider database and related reports and queries to capture contact information for potential PC component pro

Describe what you learned about the impact of economic

Describe what you learned about the impact of economic, social, and demographic trends affecting the US labor environmen