Q. Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400. Illustrate what is the probability that the project will be completed before the late-payment deadline?
_0.0401
_0.4599
_0.8056
_0.9599
_near 1.0000, or almost certain