Question 1

Analyze as well as compare the performance of the following two projects in terms of cost, schedule, and efficiency. Make sure to show your calculations as well as analyze and explain the results

Project A: The EV is $92,000 and the actual cost is $175,000. The PV is $173,000

Project B: The EV is $68,000 and the actual cost is $69,000. The PV is $71,000

Question 2

An environmental consulting firm has been appointed to clean up contaminated ground water beneath the site of a former chemical factory. The clean-up design process contains of evaluating several alternatives, preparing a theoretical design for the most appropriate alternative, appraising the conceptual design by performing a small-scale pilot test on site and based on the results of the pilot test and preparing a final design. Installation of the clean-up system will be accomplished by subcontractors under the supervision of the consultant. Before installation the consultant will work on setting up the subcontracts by preparing specifications, pre-qualifying installation contractors, studying all bids and executing the contracts. The installation will contain of the following phases- recovery wells, treatment equipment, piping, and start up

The consultant will as well be responsible for system-performance monitoring, which consists of sampling the groundwater, monitoring wells on a periodical basis and sampling the groundwater treatment-system discharge

Create a work breakdown structure (WBS) for this project with activities corresponding to a two-level task as well as subtask hierarchy. Number the WBS codes therefore that the level of each activity is clearly identified. Don't worry about indentation

Question 3

You are a project manager at a bike shop and you just received a shipment of new bikes that need to be assembled. The frames essential to be set, which contains the bike frame, handlebars and seat. The wheels require to be mounted. The braking system require to be installed. Beforehand the bike can be sold, it required to be tested by the quality team and road tested. You have accumulated your team of experts, and they are worried to get started

a) To guarantee you have a clear scope for your team, make a two-level WBS. Don't forget to comprise your WBS numbering

b) In your WBS how many work posts have been created?

Business Management, Management Studies

  • Category:- Business Management
  • Reference No.:- M9134608

Have any Question?


Related Questions in Business Management

Name a company that addressed a recent ethical problem in a

Name a company that addressed a recent ethical problem in a positive way. Also, explain how or if this positively affects us as a community?

When it is appropriate to use the trade-off process what

When it is appropriate to use the trade-off process. What conditions apply, and the technical evaluation criteria that might be used?

Need help with a essay with the following phrase for

Need help with a essay with the following phrase for analyzing : " Capitalism is at the heart of how people and organisations are managed in contemporary society" May i ask for a better explanation of the question? Also ...

How could these three tenets of the auburn creed be used to

How could these three tenets of the Auburn Creed be used to motivate others: "I believe that this is a practical word and that I can count only on what I earn. Therefore, I believe in work, hard work." "I believe in educ ...

How can these two tenets of the auburn creed by used in

How can these two tenets of the Auburn Creed by used in addressing teamwork issues: "I believe in honesty and truthfulness, without which I cannot win the respect and confidence of my fellow men." "I believe in the human ...

Discuss the advantages of having and interacting in a

Discuss the advantages of having and interacting in a diverse workplace. Consider the wide range of ideas and perspectives that a range of team members bring to a team, that are of differing ages, ethnic backgrounds and ...

Parmigiano-reggiano global recognition of geographical

Parmigiano-Reggiano: Global Recognition of Geographical Indications What historical factors have helped support the consortium's claims for the geographic specificity of Parmigiano-Reggiano and Parmesan? What are the eco ...

Communication planthis communication plan will be a roadmap

Communication Plan This communication plan will be a roadmap on how the new division will best be able to communicate with Biotech's corporate headquarters, suppliers, other divisions, and internally. This should lay out ...

Discuss strategies to obtain feedback from a customer and

Discuss strategies to obtain feedback from a customer and clients when working in sales.

Describe different networking methods and the advantages

Describe different networking methods and the advantages and disadvantages of them?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As