Construction of a highway starts February 19, 2015  & completed by year end. Delay fine of $10,000 for every week of delay pass date December 31, 2015.  So 315 days (45 weeks) for the highway project  with a seven-day work schedule.

The activities for the Highway project is as follows:

Project begins by clearing the site,  takes 8 weeks. When the site is cleared, lay subsurface drainage takes 8 weeks, followed by filling of the earth that takes 14 weeks. After these steps are completed, the installation of an artificial turf on the side of the highway begins - this activity is 12 weeks long. Simultaneously, the work on the highway can begin once the work site is cleared.

Work on the highway begins  first by excavating followed by pouring sand on the highway path. Each of these tasks takes 4 weeks each to complete. Following is the construction of layer2  (12 weeks), followed by layer3 (13 weeks). Layer4 are then completed (5 weeks) followed by layer5  (4 weeks). However, layer5 cannot be started until street lights are completed (4 weeks). The street lights cannot be started until the  electrical lines are ran underground (8 weeks), which needs an additional task of getting city of Seattle permits before it can be started. The city permit takes 4 weeks to obtain. Assume that you would start on the permits after the excavation activity for the highway begins.

Once layer3 of the highway is completed, work can start simultaneously on the street lighting (5 weeks), and on highway signage and road drawings (4 weeks). Assume you start the project on Feb 19, 2015 and  follow a seven days week  schedule where each week of an activity's duration takes 7 days.

Using the information above, use Microsoft project or excel (include the workbook with answer):

  • A. When do you complete the highway project?
  • B. How much delay $ fine would you be charged based on the estimated completion time?
  • C. Analyze each of the following proposals independently of the other proposals and comment on which proposal you adopt for expediting the project?
    • Proposal 1: Expedite layer2 construction activity - this would cost $20000 and would reduce the activity by six weeks
    • Proposal 2: The same as the above proposal but in addition, use a double shift on filling the earth. This would cost $10,000 and would reduce the filling activity by 5 weeks.
    • Proposal 3: Construction layer3 is important. You could use additional labor resource for $9,000 and cut six weeks off the original duration of the activity.
  • D. How would your analysis on the above change if the company factors in the possibility of a worker strike in the month of December?

Business Management, Management Studies

  • Category:- Business Management
  • Reference No.:- M92069266
  • Price:- $40

Priced at Now at $40, Verified Solution

Have any Question?


Related Questions in Business Management

Name a company that addressed a recent ethical problem in a

Name a company that addressed a recent ethical problem in a positive way. Also, explain how or if this positively affects us as a community?

When it is appropriate to use the trade-off process what

When it is appropriate to use the trade-off process. What conditions apply, and the technical evaluation criteria that might be used?

Need help with a essay with the following phrase for

Need help with a essay with the following phrase for analyzing : " Capitalism is at the heart of how people and organisations are managed in contemporary society" May i ask for a better explanation of the question? Also ...

How could these three tenets of the auburn creed be used to

How could these three tenets of the Auburn Creed be used to motivate others: "I believe that this is a practical word and that I can count only on what I earn. Therefore, I believe in work, hard work." "I believe in educ ...

How can these two tenets of the auburn creed by used in

How can these two tenets of the Auburn Creed by used in addressing teamwork issues: "I believe in honesty and truthfulness, without which I cannot win the respect and confidence of my fellow men." "I believe in the human ...

Discuss the advantages of having and interacting in a

Discuss the advantages of having and interacting in a diverse workplace. Consider the wide range of ideas and perspectives that a range of team members bring to a team, that are of differing ages, ethnic backgrounds and ...

Parmigiano-reggiano global recognition of geographical

Parmigiano-Reggiano: Global Recognition of Geographical Indications What historical factors have helped support the consortium's claims for the geographic specificity of Parmigiano-Reggiano and Parmesan? What are the eco ...

Communication planthis communication plan will be a roadmap

Communication Plan This communication plan will be a roadmap on how the new division will best be able to communicate with Biotech's corporate headquarters, suppliers, other divisions, and internally. This should lay out ...

Discuss strategies to obtain feedback from a customer and

Discuss strategies to obtain feedback from a customer and clients when working in sales.

Describe different networking methods and the advantages

Describe different networking methods and the advantages and disadvantages of them?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As