1. Construct a network using the AON (Activity on Network method) like we did in class.
2. Show how you calculate the path in weeks for each of the three paths.
3. Which path is the critical path?
Immediate Time
Activity Predecessor (weeks)
A --- 1
B --- 4
C A 1
D B 2
E B 5
F C, D 7
G E 2
H F, G 3