Q. Computes the multifactor productivity measure for every of the weeks shown for production of chocolate bars. Elucidate what does the productivity figure suggest? Suppose 40hour weeks also an hourly wage of R12. Overhead is 1.5 times weekly labour material cost R6 per pound. Standard price is R140 per unit.
Week Output (units) Workers Material (lbs)
1 30 000 6 450
2 33 600 7 470
3 32 200 7 460
4 35 400 8 480