Q. Computes critical ratios for subsequent activities also specify which activities are probably on targeting also which need to be investigated. Comment on every activity. Elucidate what is your overall interpretation of this result?
Activity Actual Progress Scheduled Progress Budgeted Cost Actual Cost
A 4 days 4 days $ 60 $ 40
B 3 days 2 days $ 50 $ 50
C 2 days 3 days $ 30 $ 20
D 1 day 1 day $ 20 $ 30
E 2 days 4 days $ 25 $ 25