1. Draw a project network which includes all the activities.
2. Compute the start and finish times for each activity and find out the minimum number of weeks for completing the project. Find the critical set of activities for project.
3. Recognize slack in the activities not on the project critical path.
4. Your boss would like you to suggest changes which could be made to the project that would significantly shorten it. What would you recommend?