Case Study: The Problems of Multitasking

An eastern U.S. financial services company found itself way behind schedule and over budget on an important strategic program. Both the budget and schedule baselines had begun slipping almost from the beginning, and as the project progressed, the lags became severe enough to require the company to call in expert help in the form of a project management consulting firm. After investigating the organization’s operations, the consulting firm determined that the primary source of problems both with this project in particular and the company’s project management practices in general was a serious failure to accurately forecast resource requirements. In the words of one of the consultants, “Not enough full-time [human] resources had been dedicated to the program.”

The biggest problem was the fact that too many of the project team members were working on two or more projects simultaneously—a clear example of multitasking. Unfortunately, the program’s leaders developed their ambitious schedule without reflecting on the availability of resources to support the project milestones. With their excessive outside responsibilities, no one was willing to take direct ownership of their work on the program, people were juggling assignments, and everyone was getting farther behind in all the work. Again, in the words of the consultant, “Project issues would come up and there would be nobody there to handle them [in a timely fashion].” Those little issues, left unattended, eventually grew to become big problems. The schedule continued to lag, and employee morale began to bottom out.

Following their recognition of the problem, the first step made by the consultants was to get top management to renegotiate the work assignments with the project team. First, the core team members were freed from other responsibilities so they could devote their full-time attention to the program. Then, other support members of the project were released from multitasking duties and assigned to the project on a full-time or near full-time basis as well. The result, coupled with other suggested changes by the consultants, was to finally match up the project’s schedule and activity duration estimates with a realistic understanding of resources needs and availability. In short, the program was put back on track because it was finally resource-leveled, particularly through creating full-time work assignments for the project team that accurately reflected the need to link resource management with scheduling.

Briefly summarize the situation in the case.

Explain how multitasking can create confusion in project team personnel availability.

How does multitasking or assigning employees to participate in several projects contaminate activity duration?

Why does multitasking “decouple” activity duration estimates from the project schedule?

“In modern organizations, it is impossible to eliminate multitasking for the average employee.” Do you agree or disagree? Explain your position.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M93114296

Have any Question?


Related Questions in Operation Management

Home depot is the organization and their lack of associates

Home Depot is the Organization and their lack of associates available to help when you enter the store is the area of improvement. Execute the control phase of the Six Sigma DMAIC project including the following: Determi ...

1 do you think that martha stewart violated federal

1. Do you think that Martha Stewart violated federal securities law? Why or why not? Your legal analysis aside, discuss whether you think it is fair to charge people situated similarly to Martha Stewart's position in thi ...

Hospitality human resources management1 what can be a

Hospitality Human Resources Management 1. What can be a reaction to problem solving or decision making in the workplace? How can a boss help you (not help you) work through a problem? How comfortable are you making decis ...

Shipping dronesour marketing team considered developing a

Shipping Drones: Our Marketing team considered developing a drone that could carry more weight that could be marketed to businesses rather than consumers. This shift in focus could provide for an opportunity to create mo ...

Anne is employed by cory contracting company cory has a 13

Anne is employed by Cory Contracting Company. Cory has a $1.3 million contract to build a small group of outbuildings in a national park. Anne alleges that Cory Contracting has discriminated against her, in that she has ...

Given the projected demands for the next six months prepare

Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time and overtime, and backorders. The plan must wind up with no units in ending inventory in Period 6. Regular ...

Consider all you have learned in the course so far and the

Consider all you have learned in the course so far and the trends that have been discussed, particularly around leaders being able to strategize and execute to results. Using the module readings, the Argosy University on ...

Resources ch 16 of management and appendix the project

Resources: Ch. 16 of Management and Appendix: The Project Planner's Toolkit of Management. Apply the concepts of the tools described in the Project Planner's Toolkit. After studying and evaluating the components included ...

Review michael porters five competitive strategies in

Review Michael Porter's Five Competitive Strategies in Chapter 5. Identify two companies that employ each of the strategies and cite the specific tactics/processes and strengths that the companies employ to implement the ...

1 why is there growing rivalry for inbound international

1. Why is there growing rivalry for inbound international patientst? under what conditions should a hospital make capital investments to attract international patients 2. The cleveland clinic's goal is to bring world0cla ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As