Ask Operation Management Expert

Case study : [Line Balancing in a Manufacturing Plant]

This study concerns a former division of a major UK-based manufacturer of railway rolling stock and equipment. The plant manufactures a range of bogies, which are the supporting frames and wheel sets for rail vehicles. The company has a history of supplying the passenger train market in the UK but over a period of time low demand and increased competition had led it to enter new markets including European inner-city transport and the supply of freight bogies to Far East countries. The need to compete on a global basis led the company to re-evaluate its manufacturing facility with particular emphasis on the need to increase output, reduce lead times and increase flexibility. To meet these demands management had identified areas where substantial investment was required.

The Production Process

The facility layout is on a product-line basis with the manufacturing process consisting of six main stages of fabrication, welding, frame machining, paint, fitting and quality audit. Each stage must be completed in order before the next stage can begin. The stages are now briefly described:

Fabrication. The fabrication stage prepares the bogie frame sections from sheet steel and bought-in castings. A custom template is designed from which the parts required are cut from sheet steel to standard batch sizes. Parts not needed immediately are held in storage. Processed parts and castings are brought together to form a bogie 'kit', which is assembled on a jig and taken to the subsequent welding stage.

Welding.

A bogie subassembly is manually welded on a jig at a workstation to form a main bogie frame.

Frame machining. The main bogie frame is then transferred to a CNC [computer numerically controlled machine] center for the machining of any holes or bores needed for the fixing of subassemblies such as the braking and suspension systems. Bogies are fixed to a slave table and the machine processes the frame according to a preset operation sequence. Paint. The frame is then manually painted while being suspended from an overhead moving circular track.

Fitting. Manufactured subassemblies and bought-in components such as motors are then assembled on the bogie frame. The frames are placed on supports and are moved along a line at different stages of assembly with overhead cranes. Quality audit. Final inspection is carried out to ensure all bogies meet the required specification. It is usual that a certain amount of paint touch-up work is required at this stage due to damage caused to the paint finish during the fitting stage.

The Line Balancing Study

The focus of the study was on product layout design with the main objective being to ensure that the performance of the whole manufacturing system would meet required output levels. The output level was converted into a target cycle time (time between manufacture of products or output rate). As stated, the product layout consists of six main stages with the product passing through each stage in turn. This means that the effective cycle time for the whole system is determined by the stage with the longest cycle time. The study objective was to obtain a balanced line (all cycle times equal), which would enable a smooth parts flow through the production stages facilitating the introduction of a pull-type just-in-time (JIT) production control system.

A simulation model (Chapter 8) was used to estimate the cycle time at the main manufacturing stages. The graph (Figure 4.16) shows clearly where management effort needed to be directed to achieve the target cycle time. The quality audit stage was set at a nominal amount by management. Significant problems had occurred at this stage with the spray finish on the bogie frames being damaged during the subassembly fitting stage. This had to be rectified by a manual touch-up process, which could take longer than the original spray time. The paint area would also need to be reconfigured due to new environmental controls. Management had recognized the problems and an investment in an epoxy paint plant producing a hard-wearing finish was planned. The bogie frame machining center had previously been recognized by management as a bottleneck process. The bogie frame went through a number of preprogrammed steps on the machine and the cycle time was dependent on the capability of the machining center itself. Consequently a major part of the planned investment was a new machining center with a quoted cycle time below the target. An investigation of the fabrication processes revealed that although the cycle times were above target, the majority of this time was used for machine setup. Figure 4.17 shows the effect on cycle time of a reduction in setup time of 10% to 90%.

From Figure 4.17 it is clear that a setup reduction of 50% is required to achieve the target cycle time. A team was assembled to achieve this target and it was met by the use of magnetic tables to hold parts ready for processing. The simulation was rerun and the results (Figure 4.18) show the system achieving the required performance. It can be seen that a further reduction in fabrication setup times and a reconfiguration of the welding line would reduce the overall cycle time further, producing a more balanced line and increasing capacity utilization.

By implementing the changes outlined in the study the simulation was able to predict the following improvements in performance (Table 4.6).

In the table cycle efficiency = 100%-%idle time where %idle time = idle time per cycle/total cycle time.

These are substantial improvements in performance and meet the output targets set by management. However, the results in Figure 4.18 show that further reductions in the cycle times for the fabrication and weld stages would lead to a further increase in cycle efficiency, reflecting a more balanced line, and thus a further increase in output.

Source: Excerpt from Greasley, A. (2004) "The case for the organisational use of simulation''. Journal of Manufacturing Technology Management, Vol. 15, No. 7, pp. 560-566, Emerald Group Publishing. Reproduced with permission.

Question:

1. Identify the process type used in this organisation and explain the rationale to balance a production line of a manufacturing plant. ?

2. Explain the strategies that are used to balance a production line in this case study. ?

3. Explain alternative strategies to balance a production line in a manufacturing plant.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M93116815

Have any Question?


Related Questions in Operation Management

Conflictdefine functional versus dysfunctional conflict in

Conflict Define functional versus dysfunctional conflict in a work group and explain how you can increase functional conflict and decrease dysfunctional conflict. Develop a response that includes examples and evidence to ...

For this assignment you will need to find 2 articles in

For this assignment, you will need to find 2 articles in business that can help describe what are IT strategic initiative being undertaken by an organization are like. Choose a different organization for each of the arti ...

Coping with problems joe is a little nervous he has just

Coping With Problems Joe is a little nervous. He has just been transferred from another plant to take over a production line. Production is down and there is a serious problem with absenteeism. To make matters worse, the ...

Over 30 years ago michael porter identified a holistic

Over 30 years ago Michael Porter identified a holistic approach to understanding how competitive forces shape strategy. He posited that the only way to truly insulate an organization from underlying economic volatility i ...

You are the contracting officer for an air-to-ground

You are the contracting officer for an air-to-ground missile development program. A contract for pre-production models of the missile was awarded by your predecessor and the contractor is behind schedule. In a program me ...

The ikea case provides an excellent opportunity to apply

The IKEA case provides an excellent opportunity to apply strategic management concepts to a large privately-held company that is expanding into India. IKEA is a Netherlands-based Swedish company with a presence in 44 cou ...

Can you answer for me the following questions about social

Can you answer for me the following questions about social loafing and the three main causes of free-riding. 1. Give a description of the phenomenon of social loafing. 2. Give a description of the phenomenon of free-ridi ...

1 analyzing the bridgestonefirestone and ford motor company

1. Analyzing the Bridgestone/Firestone and Ford motor company, is it sufficient to use the ISO/QS 9000 standards as the main basis of vendor/product selection? 2. What position to these cars company ( 1. Volkswagen, 2. F ...

Research the effect of primary and secondary seat belt laws

Research the effect of primary and secondary seat belt laws on the occurrence of motor-vehicle injuries and fatalities. Explain how epidemiologic studies influenced the development of current seat belt laws. Describe how ...

Please provide a brief paragrap of the key takaways from

Please provide a brief paragrap of the key takaways from each of the following topics: Designing Clear Visuals in business reports Designing Successful Documents and Websites Writing Winning Proposals

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As