Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Operation Management Expert

Case study : [Line Balancing in a Manufacturing Plant]

This study concerns a former division of a major UK-based manufacturer of railway rolling stock and equipment. The plant manufactures a range of bogies, which are the supporting frames and wheel sets for rail vehicles. The company has a history of supplying the passenger train market in the UK but over a period of time low demand and increased competition had led it to enter new markets including European inner-city transport and the supply of freight bogies to Far East countries. The need to compete on a global basis led the company to re-evaluate its manufacturing facility with particular emphasis on the need to increase output, reduce lead times and increase flexibility. To meet these demands management had identified areas where substantial investment was required.

The Production Process

The facility layout is on a product-line basis with the manufacturing process consisting of six main stages of fabrication, welding, frame machining, paint, fitting and quality audit. Each stage must be completed in order before the next stage can begin. The stages are now briefly described:

Fabrication. The fabrication stage prepares the bogie frame sections from sheet steel and bought-in castings. A custom template is designed from which the parts required are cut from sheet steel to standard batch sizes. Parts not needed immediately are held in storage. Processed parts and castings are brought together to form a bogie 'kit', which is assembled on a jig and taken to the subsequent welding stage.

Welding.

A bogie subassembly is manually welded on a jig at a workstation to form a main bogie frame.

Frame machining. The main bogie frame is then transferred to a CNC [computer numerically controlled machine] center for the machining of any holes or bores needed for the fixing of subassemblies such as the braking and suspension systems. Bogies are fixed to a slave table and the machine processes the frame according to a preset operation sequence. Paint. The frame is then manually painted while being suspended from an overhead moving circular track.

Fitting. Manufactured subassemblies and bought-in components such as motors are then assembled on the bogie frame. The frames are placed on supports and are moved along a line at different stages of assembly with overhead cranes. Quality audit. Final inspection is carried out to ensure all bogies meet the required specification. It is usual that a certain amount of paint touch-up work is required at this stage due to damage caused to the paint finish during the fitting stage.

The Line Balancing Study

The focus of the study was on product layout design with the main objective being to ensure that the performance of the whole manufacturing system would meet required output levels. The output level was converted into a target cycle time (time between manufacture of products or output rate). As stated, the product layout consists of six main stages with the product passing through each stage in turn. This means that the effective cycle time for the whole system is determined by the stage with the longest cycle time. The study objective was to obtain a balanced line (all cycle times equal), which would enable a smooth parts flow through the production stages facilitating the introduction of a pull-type just-in-time (JIT) production control system.

A simulation model (Chapter 8) was used to estimate the cycle time at the main manufacturing stages. The graph (Figure 4.16) shows clearly where management effort needed to be directed to achieve the target cycle time. The quality audit stage was set at a nominal amount by management. Significant problems had occurred at this stage with the spray finish on the bogie frames being damaged during the subassembly fitting stage. This had to be rectified by a manual touch-up process, which could take longer than the original spray time. The paint area would also need to be reconfigured due to new environmental controls. Management had recognized the problems and an investment in an epoxy paint plant producing a hard-wearing finish was planned. The bogie frame machining center had previously been recognized by management as a bottleneck process. The bogie frame went through a number of preprogrammed steps on the machine and the cycle time was dependent on the capability of the machining center itself. Consequently a major part of the planned investment was a new machining center with a quoted cycle time below the target. An investigation of the fabrication processes revealed that although the cycle times were above target, the majority of this time was used for machine setup. Figure 4.17 shows the effect on cycle time of a reduction in setup time of 10% to 90%.

From Figure 4.17 it is clear that a setup reduction of 50% is required to achieve the target cycle time. A team was assembled to achieve this target and it was met by the use of magnetic tables to hold parts ready for processing. The simulation was rerun and the results (Figure 4.18) show the system achieving the required performance. It can be seen that a further reduction in fabrication setup times and a reconfiguration of the welding line would reduce the overall cycle time further, producing a more balanced line and increasing capacity utilization.

By implementing the changes outlined in the study the simulation was able to predict the following improvements in performance (Table 4.6).

In the table cycle efficiency = 100%-%idle time where %idle time = idle time per cycle/total cycle time.

These are substantial improvements in performance and meet the output targets set by management. However, the results in Figure 4.18 show that further reductions in the cycle times for the fabrication and weld stages would lead to a further increase in cycle efficiency, reflecting a more balanced line, and thus a further increase in output.

Source: Excerpt from Greasley, A. (2004) "The case for the organisational use of simulation''. Journal of Manufacturing Technology Management, Vol. 15, No. 7, pp. 560-566, Emerald Group Publishing. Reproduced with permission.

Question:

1. Identify the process type used in this organisation and explain the rationale to balance a production line of a manufacturing plant. ?

2. Explain the strategies that are used to balance a production line in this case study. ?

3. Explain alternative strategies to balance a production line in a manufacturing plant.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M93116815

Have any Question?


Related Questions in Operation Management

You are the director of global compliance for a us company

You are the Director of Global Compliance for a U.S. company that just created a revolutionary new portable personal computer (PPC) that is half the size of a laptop, performs the same functions as existing laptop comput ...

Youre writing a proposal to institute the practice of

You're writing a proposal to institute the practice of telecommuting at work. You work for a non-profit community organization of 40 full-time employees, most of whom do most of their work at computers. Some employees (a ...

Comment this discuss can leaders really motivate

Comment this Discuss : Can Leaders Really Motivate Employees? A successful organization is an organization that knows how to take advantage of the efficiency and effectiveness of its staff. The researchers worked to obta ...

1 how do customer characteristics influence global

1. How do customer characteristics influence Global Distribution channel design? 2. List three common problems that can occur when traditional critical path scheduling is used. How would you address each? 3. What led the ...

1 discuss the following approaches to discipline hot-stove

1. Discuss the following approaches to discipline: hot-stove rule and progressive discipline. 2. Of the various activities listed in Luther Gulick's POSDCORB, are there any other activities you would add that occur on or ...

You and four friends have developed a new environmentally

You and four friends have developed a new environmentally friendly heater. You all have extensive business experience. Together, you have established a new company, Green Heaters Pty Ltd ACN 512 302 XXX, which will manuf ...

1 yoursquore working at a local hospital and have been

1. You’re working at a local hospital and have been given the task of planning to provide flu shots for the upcoming flu season. You anticipate very heavy demand because of the nature of this season’s flu. You anticipate ...

True or false to these questionsan executives discretion

True or false to these questions An executive's discretion and impact on a public policy issue increases as the issue matures over time. Under the business judgment rule, all states prevent officers and directors from ta ...

Major information systemscoursesnet work database

Major: Information systems Courses:(Net work , Database, Technical Communications, Communicating and Documenting Information Systems , Analysis for Database Design, Information systems Analysis, Human-Computer Interactio ...

1 how convincing is the evidence that medicaid agencies are

1. How convincing is the evidence that Medicaid agencies are getting better value for their money when they contract with HMOs? 2. As a leader, how might you overcome your own felt resistance to a change from above and a ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As