Based on the table, perform resource limited scheduling. Assume that each task can perform independently from the other tasks. Assume that only 2 workers are availible at any given time. What is the new completion date for the project
Task
1
2
3
4
5
Workers Needed
2
1
1
1
1
Scheduled Days
1,2,3,4,5,6,7,8
7,8,9,10
1,2,3,4
1,2,3,4,5,6
11,12