| Task |
Task Time(seconds) |
Immediate Predecessor |
| A |
45 |
- |
| B |
11 |
A |
| C |
9 |
B |
| D |
50 |
- |
| E |
26 |
D |
| F |
11 |
E |
| G |
12 |
C |
| H |
10 |
C |
| I |
9 |
F, G, H |
| J |
10 |
I |
| |
|
|
| |
193 |
|
| |
|
|
| |
Balance the line using the largest positional weight heuristic. Break ties with the most following tasks heuristic. Use a cycle time of 50 seconds.
Work stations Following Tasks
I
II
III
IV
V
Calculate the percentage idle time for the line. (Round your answer to 1 decimal place. Omit the "%" sign in your response.)