Q. A consulting industry is planning a reengineering project for a client. subsequent ac¬tivities and time approximates have been identified:
Activity Time, Days Immediate Predecessor
A 1 -
B 2 -
C 2 -
D 2 A,B
E 4 A,C
F 1 C
G 4 D
H 8 G,E,F
a. Draw a project ne2rk diagram.
b. Compute scheduling times and total slack for each activity.
c. List critical path activities and project duration.
d. Assuming that 1 worker is required for each activity, prepare a resource-levelled schedule. Illustrate what is maximum number of workers required to finish project on time?