Assume you have completed three months of the project. The BAC was $200 000 for this six month project. Also assume the following: PV = $120,000 EV = $100,000 AC = $90,000 a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? c) Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91630657

Have any Question?


Related Questions in Operation Management

1 compute the takt time minutes per unit for a system given

1. Compute the takt time (minutes per unit) for a system given the following data: There are 4 worker(s) per shift with one worker's total time per shift of 450 minutes. There is/are 3 shift(s), and workers are given two ...

A title of the ama webinarrsquos topicin detail what issues

A title of the AMA webinar’s topic. In detail, what issue(s) covers in the webinar, and what is the main topic(s) of the webinar? In detail, which point(s) can be connected the contents from the perspective of marketing? ...

What are valuesethicswhat are they forwhat is the ethical

What are values/ethics? What are they for? What is the ethical obligation of an organization? Is it important to define organizational values? Describe a Defining Moment for you, when your personal values did not align w ...

Identify at least two distinct market segments for tesla

Identify at least two distinct market segments for Tesla model S or X. Each market segment description must include at least three (more if needed) of the characteristics from amongst any of the four bases categories, e. ...

Identify and describe a healthcare delivery organization or

Identify and describe a healthcare delivery organization or hospital close to you or for which you have a special interest. Review its annual report online and compile a brief that responds to each of the elements listed ...

1 explain a surgical team as a kind of functional group

1. Explain a surgical team as a kind of functional group. What features does it share with most functional groups? What features distinguish it from most functional groups? 2. Explain a surgical team in terms of its role ...

1 a bitcoin payment service might receive thousands of

1. A Bitcoin payment service might receive thousands of payments from various users near-simultaneously. How can it tell whether a particular user Alice who logged into the payment service website and initiated the payme ...

Integrated approach to health care quality management a

Integrated approach to health care quality management: a case study Prasanta Kumar Dey And Seetharaman Hariharan In this case, the authors developed an integrated quality management model, which detects the problems, iss ...

1 discuss at least five risks and perils that are present

1. Discuss at least five risks and perils that are present in global transportation, and how exporters and importers can manage these risks. Substantiate your answer with referenced examples. 2. Describe the types of tra ...

1 what is the major advantage of air carriers how does this

1. What is the major advantage of air carriers? How does this advantage impact the inventory levels of those firms using air transportation? Explain how this advantage relates to the choice of modes when choosing between ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As