Assume that you are the project manager for the construction of 10 conference facilities in your organization’s building in Florida. A statement of work has been given to you, and contracts have already been awarded. The project will require you to do the following for one of the conference facilities:

Install new electrical outlets and light fixtures: ABC Electrical Company (fixed price contract $20,500, week 1).

Install multimedia capability: Sound Masters, Inc. (fixed price contract $40,000, week 1 and $23,300, week 4).

Finish walls and apply custom paint color—Ocean Blue #4495: K&G Painters (cost reimbursable contract $24,990, week 2).

Install carpeting (color # 9984) and window shades (color # 5574): Best Flooring and Windows (fixed price contract $46,340, half in week 2 and half in week 3).

Install new furniture to match wall color (#4495), including 20 custom-made tables and 80 extra plush ergonomic chairs with wheels: Custom Furniture Experts, LLC (cost reimbursable contract $87,300, one quarter in week 1 and balance in week 4).

Install new furniture to match wall color (#4495), including 20 custom-made tables and 80 extra plush ergonomic chairs with wheels: Custom Furniture Experts, LLC (cost reimbursable contract $87,300, one quarter in week 1 and balance in week 4).

Complete inspection and acceptance within one month.

The 10 conference facilities will be worked on sequentially. Each conference facility is completed and ready for inspection before work can begin on the next facility. That means that your project is 10 months long and consists of 10 subprojects for each conference facility.

This is a high-visibility project, and the completion date is firm because your company is hosting a very important client meeting in the first conference facility in 45 days. The balance of the conference facilities have similar meetings already set up for their projected completion dates. Defaulting on the schedule is not an option.

You have a project team to help with the oversight and inspection of the project, which includes you and two technicians. Your salary is $1,050 per week and your technicians earn $13 per hour. You expect both of them to work 20 hours per week for the first three weeks and 40 hours in the last week of each conference facility subproject. However, one of your technicians may have surgery scheduled before the end of your first conference room subproject, which will result in you working additional hours. The decision on the surgery has not yet been made by his doctors. You will work 30 hours each week, without taking the potential employee absence into account. Your company overhead rate is 89% of labor and is not applied to vendor contracts. All materials are included in the vendor contracts. Artwork for a room this size could run between $10,000 and $15,000, depending on the quality of the frames. Your organization’s leaders want to impress their clients in this new facility, so you assume that the highest quality frames should be purchased.

Hurricane season just began, and you have seen reports of a major storm heading toward your town. You may have to evacuate, or worse yet, the facility could be damaged by the storm at the end of the first week of the first conference facility subproject. Evacuation would cause a one-week slip, and facility damage could cause a three-week slip, which would affect all the subsequent subprojects.

It is important that all contractors perform their work according to their contractual schedule. Any slip of one contractor will impact the next contractor’s beginning date.

Using this information, create a time-phased budget baseline on a spreadsheet. This baseline will consist of the incremental cost for each week, in addition to a cumulative cost for each week for 10 months.

Answer the following questions:

How do schedule considerations add to your project risk?

Which risks have the greatest potential to disrupt your project? Why?

Do you think you need contingency for this project? Why? How much?

What role do your risks play in your contingency estimate?

Submit the project baseline in an Excel spreadsheet.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91700214

Have any Question?


Related Questions in Operation Management

Assignment discussion-ethics and ipripr protect drug

Assignment : Discussion-Ethics and IPR IPR protect drug companies from others making their products without the expense of investing in research and development. IPR also enable drug companies to recoup research and deve ...

According to the retail section process model spiggle and

According to the Retail Section Process Model (Spiggle and Sewall 1987), it is assumed that consumers follow five steps before the purchase of any product at the selected retail store: awareness, evoked, action, interact ...

What would happen to a business without a marketing

What would happen to a business without a marketing strategy? explain why based on your answer. What is the difference between a pull system and a push system of inventory control? Explain briefly 9 possible differences ...

1 why is an audit considered to be the final phase of a

1. Why is an audit considered to be the final phase of a budgetary process? 2. C&A uses a line of 5 stations to make a product. The cycle time is 30 seconds per unit. The inventory between stations is 10 units. Inspectio ...

What contributions can high self-monitors make in

What contributions can high self-monitors make in organizations? Low self-monitors? Conduct additional research on self-monitoring to add in answer the question. How can managers increase their employee's job satisfactio ...

Company a is a manufacturer of gaming machines in a recent

Company A is a manufacturer of gaming machines. In a recent investigation by the Corruption Agency that they have been alleged to offer incentives to the members of the parliament to support a proposed bill which would a ...

1 you have been asked to explain to employees that you

1. You have been asked to explain to employees that you supervise what a business plan is and why it is important to have a business plan that focuses on customer service. Write a transcript of what you would say to them ...

1 what holiday inn hotel has developed in term of

1. What Holiday Inn Hotel has developed in term of technology dimension? ( please write 3 or 4 points) with more details 2. Explain in your own words what role the "clear and present danger" test once played in First Ame ...

Scenario you are a sole proprietor presenting to a group of

Scenario: You are a sole proprietor presenting to a group of investors, seeking 20 million dollars to raise capital for your solar panel manufacturing and installation company, Solar Co. Prepare a 7- to 10-slide Microsof ...

You are wanting to change the financial structure of a

You are wanting to change the financial structure of a healthcare organization. Once the change is successful, you will always be looking for ways to change to make things better, more efficient, more cost-effective, etc ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As