Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Homework Help/Study Tips Expert

Assignment

The purpose of this assignment is for the student to design an electrical distribution system for the coal mine illustrated in Figure.

1179_figure.jpg

Figure 1: schematic diagram of underground workings.

The mine is to operate a single retreating long wall coalface at any one time. Whilst this face (panel 1 on the figure) is in production the next panel is under development. The physical dimensions of each airway in the system are as listed in Table 1. All airways excepting the drift and shaft are developed fully within the flat coal seam of 3m thickness. A ventilation fan is located at the top of the return ventilation shaft that can in emergency situations act as a second means of egress.

Coal clearance is undertaken by conveyor, conveyors are located in airways 1-2, 2-5, 5-7, 5-6, 7-10, 10-11, 11-12, 12-13 and 7-14 with an armoured face conveyor located on ht face 6-8. Development is undertaken using continuous miner. Table 2 lists the electrical machine requirements and location for the time frame under consideration.

Distribution voltage at the mine is 13.2 kV.

The purpose of the exercise is to devise an electrical distribution system to service the current and possible future requirements of the mine. The student is to consider the following:

- Cables and cable couplings
- Switchgear
- Transformers
- Power centres
- Distribution and utilisation systems
-Electrical safety
- Control requirements
- Any other requirements
- Power factor correction (if required)

All assumptions need to be detailed and justified. The results should be presented as a report; no page limit is specified, with diagrams and other data as required. Students should note that there is no single answer to this design, marking will be based on the robustness of the system, the inherent safety of the system and the ability of the system to be expanded. In order to aid on the last criterion it is expected that the life of an individual panel is of the order of 6 months under the current production schedule, the extracted length of all panels in the mine is 1950m, i.e. a 50 m barrier pillar is required.

Table 1: Dimensions of mine.

Branch from

Branch to

Length (m)

Width (m)

Height (m)

Comments

1

2

2400

5

4

Intake drift 1 in 6

2

3

200

5

3

Cross cut

2

5

150

5

3

Intake

5

7

100

5

3

Intake

5

6

2000

5

3

Panel 1 intake airway

6

8

250

5

3

Panel 1 face

8

9

2200

5

3

Panel 1 return airway

7

10

650

5

3

Intake

10

11

200

5

3

Cross cut

11

12

400

5

3

Return

12

13

500

5

3

Panel      2    return      airway      dead      end

development

12

9

100

5

3

Return

7

14

2150

5

3

Panel 2 intake airway development

9

3

350

5

3

Return airway

3

4

400

4.5

 

Return shaft (circular)

Table 2: Major items of electrical equipment to be considered within the exercise

Item of equipment

location

Power (kW)

Voltage (V mis)

Comments

Panel     1     shearer

(coal cutter)

Anywhere on coal face

500

1100

Max length of cable from intake end of face = 250m

Panel       1      return

end AFC drive

Node 8

350

1100

Directly         coupled        to

intake end AFC motor

Panel       1      intake

end AFC drive

Node 6

350

1100

Directly         coupled        to

return end AFC motor

Stage              loader

motor

200m from node

6      in      panel      1
intake

250

1100

Phased to start prior to AFC

Panel 1 hydraulic power pack

150m from node

6

2 x 180

1100

2 x 110 kW pumps

Panel                      1

Ancillaries

130m from node 6

po

550

Max length of cable from here is 380m

Panel 1 belt drive

Node 5

400

1100

 

Main belt drive

Node 2

450

1100

 

Main       drift       belt

drive

Node 1

2 x400

1100

 

Panel       2      intake

drive          conveyor
drive

Node 7

400

1100

 

Cross                   cut

conveyor drive

Node 10

150

1100

 

Return conveyor drive

Node 11

225

1100

 

Panel      2       return

conveyor drive

Node 12

350

1100

 

Panel                      2

continuous miner (return drive)

Node 13

550

1100

 

Panel                      2

continuous miner (intake drive)

Node 14

550

1100

 

Main fan

Node 4

330

550

Axial flow fan

Pump station

50m from node 2

55

550

Mine drainage (water)

Auxiliary fan

Node 7

150

550

Services airway 7-14

Auxiliary fan

Node 7

150

550

Services airway 7-10

Auxiliary fan

Node 12

150

550

Services airway 12-13

Assignment 2

If required it may be assumed that g = 9.81 m/s2, Density of water = 1000 kg/m3, You are a mine planning engineer at a medium sized operation producing 1.5 mtpa of coper ore at 3% Cu. The mine was originally designed using a bench height of 15m. Footwall benches were 15 m wide to give a slope angle of 45°, but on the hanging wall side alternate benches are only 10m wide to produce an angle of about 50°.

You are required to design a drainage and pumping system to deal with the mine water for the next 10-15 years based on the data in the following sections. As the mine grade is low and power costs are high every effort should be made to minimise the operating costs of the pumping system. Describe your proposed drainage and pumping system with the aid of diagrams where required and explain the general philosophy behind the system. Detail and assumptions made and make comments and conclusions as required.

Data

Mine water

Ground water: currently averages 1,000,000 litres/day and is expected to increase at a rate of 5% per year as the mine deepens.
Mine water: averages 50,000 l/day with small variations in use on an hour by hour basis.
Water Quality: Run of mine water is expected to be slightly acidic due to the formation of sulphuric acid from sulphides within the rock

Rock properties: SG of 2.9 for all rocks. Hanging wall and ore have moderate strength, footwall is very strong.

91_Rock properties.jpg

Mine Selection

Rainfall: the average annual rainfall s 740 mm, the average monthly figures are as follows

January                                               10mm

February                                              10mm

March                                                  40mm

April                                                                       60mm

May                                                     80mm

June                                                    100mm

July                                                     110mm

August                                                120mm

September                                           90mm

October                                               60mm

November                                            40mm

December                                            20mm

Based on measurements in the locality the maximum rainfall intensity recorded over the last 50 years is as indicated below and needs to be accounted for:

Storm duration (hours)

Intensity (mm/hr)

2

40

4

25

8

15

12

12

16

10

20

9

24

8

36

6

48

5

10) For the system indicated below determine the following:
d) The Average Power on the low winding side of the transformer kW
e) The reactive power kVAR
f) The effective power kVA
g) The power factor
h) The Current I1

351_figure1.jpg

26) The following data presented is from a nest of piezometers installed side by side at a single site.

Piezometer

A

B

C

Elevation  at   surface    (m

Al-ID)

850

790

830

Depth of piezometer (m)

150

100

50

Depth to water (m)

37

42

26

If A, B and C refers to the points of measurement of piezometers a, b and c, determine:
a) The hydraulic head, pressure head and elevation head at A, B and C
b) The vertical hydraulic gradients between A and B, and between B and C if they are spaced 200m apart

36) A 100 kW, 450V AC shuttle car uses a flat cable. Two layers of the cable will remain on the shuttle car's reel at all times. What is the required ampacity for the cable if efficiency is 80%, a power factor of unity also applies.

17. For the ventilation network shown on the next page, determine the flow and pressure drop in each branch of the network.

1131_figure2.jpg

18) For the following
Face dimensions 5.5 m high by 6 m wide
Face advance 3.5 m
Length of development before blast 250m
Rock density 3 tonnes/m3
ANFO factor 2.5 kg/m3 rock broken
Face ventilation 30m3/s
NO2 gas production rate 3.5 kg per tonne of ANFO
NO2 TWA is 3 ppm

Determine
1. Volume of rock to be blasted
2. Tonnes of rock to be blasted
3. ANFO used
4. Fume throw back distance
5. Volume of fumes immediately after the blast
6. Volume of NO2 gas produced
7. Concentration of NO2 in fume throw back zone immediately after the blast
8. Concentration of fumes after they have spread throughout the drive but before they have entered the decline
9. Time for diluted fumes to fill the drive
10. Time for fumes to be diluted below TWA concentration
11. Total time for fumes to clear

Homework Help/Study Tips, Others

  • Category:- Homework Help/Study Tips
  • Reference No.:- M93126102
  • Price:- $120

Guranteed 48 Hours Delivery, In Price:- $120

Have any Question?


Related Questions in Homework Help/Study Tips

Research questionshow much does existing building

Research Question(s) How much does existing building contribute to GHG emissions? How to reduce carbon footprint of existing building and making them greener? How does green technology reduce the amount of carbon footpri ...

Assignmenttruth is the key to making good and well-informed

Assignment Truth is the key to making good and well-informed decisions in management. However, criminal justice organizations in some jurisdictions do not practice the ethics of truth. They do not create trust in their a ...

Dumpster inc is a financial consulting company that for a

Dumpster, Inc. is a financial consulting company that, for a fee, advises clients how to manage and invest their money. Dumpster operates in the fictitious state of New Manitoba and has more than 30 employees and more th ...

Question first major paper assignment arguing for a

Question: First Major Paper Assignment: Arguing for a Definition of Higher Education Description: Make an argument to define higher educationin a way that readers will find illuminating given the essays and excerpts from ...

Question 1 you are working as a tax consultant in mayfield

Question 1 You are working as a tax consultant in Mayfield, NSW. Your client is an investor and antique collector. You have ascertained that she is not carrying on a business. Your client provides the following informati ...

Section a terminology and short answerattempt all questions

Section A. Terminology and Short answer Attempt all questions in this section. The value of each question is as shown. Answer these questions in the answer booklet that is provided. Question 1. Define each of the followi ...

Differentiated instruction powerpoint instructionsthe

DIFFERENTIATED INSTRUCTION POWERPOINT INSTRUCTIONS The purpose of this assignment is to produce aPowerPointpresentation that demonstratesyour ability to apply course concepts and vocabulary to the topic of differentiated ...

Question 1 why should the governments focus should be on

Question: 1. Why should the government's focus should be on productivity not employment? 2. Why is the decentralization of government power good for economy? 3. Estimating unknown model parameters, such as the sensitivit ...

Question there are several types of fallacies -

Question: There are several types of fallacies - equivocation, false authority, ad hominem, appeal to ignorance, and bandwagon. Please provide two (2) different examples of advertising that show any of the above topics. ...

Read on the ethics of therapists do you think that having a

Read on the ethics of therapists, do you think that having a degree in psychology or a license to practice psychology makes a person a competent psychologist? Explain your answer in detail elaborating on what defines a c ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As