Moore Housing Contractors is negotiating a deal with Countryside Realtors to build six houses in a new development. Countryside wants Moore Contractors to start in late winter or early spring when the weather begins to moderate and build through the summer and fall. The summer months are a busy time for the realty company, and it believes it can sell the houses almost as soon as they are ready or sometimes before. The houses all have similar floor plans and are of approximately equal size; only the exteriors are noticeably different. The completion time is so critical for Countryside Realtors that it is insisting a project management network accompany the contractor's bid for the job with an estimate of the completion time for a house. The realtor also needs to be able to plan its offerings and marketing for the summer. The realtor wants each house to be completed within 45 days after it is started. If a house is not completed within this frame, the realtor wants to be able to charge the contractor a penalty. Mary and Sandy Moore, the president and vice president of Moore Housing Contractors, are concerned about the prospect of a penalty. They want to be confident they can meet the deadline for a house before entering into any agreement with a penalty involved. If there is a reasonable likelihood they cannot finish a house within the 45 days, they want to increase their bid to cover potential penalty charges. The Moores are experienced home builders, so it was not difficult for them to list the activities involved in building a house or to estimate activity times. However, they made their estimates conservatively and tended to increase their pessimistic estimates to compensate for the possibility of bad weather and variations in their workforce. Following is a list of the activities for building a house and the activity estimates:

Activity

Description

Predecessors

Time (days)

a

m

b

A

Excavation, pour footers

-

3

4

6

B

Lay foundation

A

2

3

5

C

Frame and roof

B

2

4

5

D

Lay drain tiles

B

1

2

4

E

Sewer (floor) drains

B

1

2

3

F

Install insulation

C

2

4

5

G

Pour basement floor

E

2

3

6

H

Rough plumbing, pipes

E

2

4

7

I

Install windows

F

1

3

4

J

Rough electrical wiring

F

1

2

4

K

Install furnace, air conditioner

C, G

3

5

8

L

Exterior brickwork

I

4

6

10

M

Install plasterboard, mud, plaster

J, H, K

6

8

12

N

Roof shingles, flashing

L

2

3

6

O

Attach gutter, downspouts

N

1

2

5

P

Grading

D, O

2

3

7

Q

Lay subflooring

M, N

3

4

6

R

Lay driveway, walks, landscape

P

4

6

10

S

Finish carpentry

Q

3

6

12

T

Kitchen cabinetry, sink, and appliances

Q

2

4

8

U

Bathroom cabinetry, fixtures

Q

2

3

6

V

Painting (interior and exterior)

S, T, U

4

6

10

W

Finish wood floors, lay carpet

S, V

2

5

8

X

Final electrical, light fixtures

V

1

3

4

  1. Develop a CPM/PERT network (draw the network, find expected completion time, variances, ESTs, LSTs, EFTs, LFTs, and slack for each activity, and expected project completion time and critical path).
  2. Determine the probability that the contractors can complete a house within 45 days.
  3. Does it appear that the Moores might need to increase their bid to compensate for potential penalties?
  4. Indicate which project activities Moore Contractors should be particularly diligent to keep on schedule by making sure workers and materials are always available.
  5. Indicate which activities the company might shift workers from as the need arises.

The Moores also developed the budget for building a house. The budget estimates before project start is provided in the table below:

Activity

Total budgeted cost ($)

A

$20,000

B

$21,000

C

$25,000

D

$5,000

E

$6,000

F

$4,000

G

$15,000

H

$11,000

I

$8,000

J

$7,000

K

$6,000

L

$13,000

M

$6,000

N

$3,000

O

$2,500

P

$3,500

Q

$8,000

R

$11,000

S

$9,000

T

$8,000

U

$4,000

V

$6,000

W

$8,000

X

$2,000

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  1. Develop budgeted cost estimates per day from the start of the project until its completion using both ESTs and LSTs of each activity.

In the 12th day of the project, the Moores wanted to know the status of the project. Activities A, B, C, D, and E have been finished and incurred costs of $19,000, $24,000, $25,000, $4,000, and $8,000, respectively. Activity G is 80% finished with incurred costs of $13,000, activity H is 60% finished with incurred costs of $7,000, and activity F was just started (5% completed) and incurred a starting cost of $600. The other activities have not been started.

  1. Is the project of building the first house on schedule?
  2. What is the value of work completed?
  3. Are there any cost overruns?

Suppose the Countryside Realtors wanted to have each house finished in 35 days. Moore Contractors has a plan developed for this type of situation, as well. This plan includes adding extra resources such as equipment and people to each of the activities A - X needed for building a house. The crash time and crash cost for each activity are presented in the table below:

Activity

Crash time

Crash cost

A

3

$28,000

B

2

$26,000

C

3

$31,000

D

1

$6,500

E

1

$7,000

F

3

$5,000

G

2

$18,000

H

3

$12,000

I

2

$10,000

J

1

$7,500

K

3

$9,000

L

3

$19,000

M

6

$8,000

N

1

$4,000

O

1

$3,000

P

2

$4,000

Q

3

$10,000

R

4

$13,000

S

3

$12,000

T

3

$9,000

U

2

$6,000

V

5

$9,000

W

4

$9,000

X

1

$4,000

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  1. Calculate the project crash cost under this scenario.
  2. Using the crash time and crash cost in the table above, calculate the shortest possible delivery time and its cost.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91263435
  • Price:- $30

Guranteed 24 Hours Delivery, In Price:- $30

Have any Question?


Related Questions in Operation Management

Adj enterprises produces hydrothermocorticoids consider the

ADJ Enterprises produces hydrothermocorticoids. Consider the following facts about ADJ and the hydrothermocorticoid market: For each of the past three years, ADJ has earned the following profits: a Net Profit Margin of 6 ...

As a leader you often need to display or clarify a concept

As a leader, you often need to display or clarify a concept. A matrix is a grid that contains information and offers a visual model of ideas. For this assignment, you will create a matrix that explains leadership theorie ...

An end itemrsquos demand forecasts for the next 10 weeks

An end item’s demand forecasts for the next 10 weeks are 30, 20, 35, 50, 25, 25, 0, 40, 0, and 50 units. The current on-hand inventory is 80 units. The order policy is to produce in lots of 100. The booked customer order ...

1 tell me about a hypothesis that you would like to test

1. Tell me about a hypothesis that you would like to test that relates to marketing/consumer behavior. What is the null hypothesis? What is the alternative hypothesis? 2. Explain the principle of unjust enrichment. 3. Pr ...

-which structureapproach can suffer from communication

-Which structure/approach can suffer from communication barriers and conflict between departments, difficulty in coordinating products and services, and a focus on departmental rather than organizational goals? -Control ...

Select an industry that you are familiar with or that you

Select an industry that you are familiar with or that you work in (the industry is Bose). Address the following questions within the context of that industry: Classify firms in that industry according to the four roles d ...

Identify at least two distinct market segments for tesla

Identify at least two distinct market segments for Tesla model S or X. Each market segment description must include at least three (more if needed) of the characteristics from amongst any of the four bases categories, e. ...

Porters five forces model is the most popular tool for

Porter's five forces model is the most popular tool for analyzing the level of competition in an industry. Considering your own industries, answer the following questions: Which are the primary sources of competitive int ...

This week please use a company again to select a plant

This week, please use a company again to select a plant asset (building, fixtures, large equipment, vehicles, etc.) that the company purchases to use in the business operations. Describe the asset for us and give us esti ...

Analyze how iso 14001 and aa1000 regulations protect

Analyze how ISO 14001 and AA1000 regulations protect stakeholders. Do these regulations and reports have an impact on how investors see the long-term viability of an organization or company in which they plan to invest? ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As