Assignment

Question 1
The first step in the project control process of the measurement and evaluation of project performance is to

Set a baseline plan
Determine the project objectives
Determine the project deliverables
Analyze the project budget
Review the project priority matrix

Question 2
The third step in the project control process of the measurement and evaluation of project performance is to:

Review the baseline plan with top management
Analyze inputs to the control system
Compare the plan against actual performance
Measure both progress and performance
Review spending with team members

Question 3
A project monitoring system involves all of the following except:

Determining what date to collect
Determining how, when, and who will collect the data
Adjusting the data
Analysis of the data
Reporting current progress

Question 4
The last step in the project control process of the measurement and evaluation of project performance is to:

Take appropriate action
Prepare a report to top management
Follow up on corrective action
Measure progress and performance
Review spending with team members

Question 5
The percent complete index that looks at percent complete in terms of actual amounts is calculated by which of the following?

EV/BAC
(EV-PV)/BAC
AC/EAC
(EV-AC)/BAC
(EV-PV)/EAC

Question 6
The second step in the project control process of the measurement and evaluation of project performance is to:

Review the baseline plan with top management
Analyze inputs to control system
Compare plan against actual
Measure progress and performance
Review spending with team members

Question 7
Small refinements that eventually build to be major changes are known as:
Project erosion
Scope creep
Specification adjustments
Specification refinements
Continuous improvements

Question 8
In monitoring project time (schedule) performance actual performance should be compared to:

Budgets for the current year
Top management's targets
Project network schedule derived from the WBS/OBS
Progress on similar past projects
Previous status reports

Question 9
Implementing closedown includes the following major activities except:

Getting delivery acceptance from the customer.
Shutting down resources and releasing to new uses.
Closing accounts and seeing all bills are paid.
E-mail the project team that the project is complete.
Creating a final report.

Question 10
In the Snapshot from Practice, New Balls Goes Flat in NBA, is an example of a project gone wrong when the _______ is/are not consulted.

Manufacture
Equipment and facilities managers
End-users
The Fans
Project manager

Question 11
__________ of lessons learned are designed to improve performance on current and future projects.

Retrospectives
Corrective action plans
Introspective
Culmination
Evolution

Question 12
Many projects will fail because of circumstances beyond the control of the project team is called:

Normal
Premature
Perpetual
Failed Project
Changed Priority

Question 13
The section of the final project report that new project teams are likely to find most useful is the:

Analysis
Recommendations
Classification of project
Lessons learned
Strategic objectives

Question 14
When the project may be completed early with some parts of the project eliminated this is considered to be ___________ closure.

Normal
Premature
Perpetual
Changed Priority
Failed Project

Question 15
Items technical in nature and focus on solutions to problems that surfaced would typically appear in the _____ section of the final project report.

Analysis
Recommendations
Classification of project
Lessons learned
Strategic objectives

Question 16
When a project may start with a high priority but see its rank erode or crash during its project life cycle as conditions change this is an example of:

Normal
Premature
Perpetual
Failed Project
Changed Priority

Question 17
Which of the following is responsible for the continued support of consistent application of selection criteria, standards, processes, training, and general assistance to project managers and continued improvement and use of best practices?

Portfolio Project Management
Project Office Management
Project Management Optimization
Project Priority Matrix Management
Resource Allocation Optimization

Question 18
Which of the following is not one of the techniques to insure that projects meet the needs of the organization?

Standards
Procedures
Accountability
Controls

Question 19
The use of an organization-wide project management system tailored to specific needs of the organization is established in which of the following Maturity Model Levels?

Ad Hoc Project Management
Formal Application of Project Management
Institutionalization of Project Management
Management of Project Management System
Optimization of Project Management System

Question 20
The importance of the increase in project oversight to today's project manager includes all of the following except:

Increase in expected profits from projects
Increased interest in supporting and helping the project manager
Impact on the environment in which the project will be implemented
Impact on how the project manager's performance will be measured
The reporting of project progress to an oversight group

Question 21
Which of the following is not one of the four performance goals measures in the scorecard model?

customer
internal
financial measures
industry standards
innovation and learning

Question 22
The first appearance of standard approaches to managing projects including scope statements and WBS occurs in which of the following Maturity Model Levels?

Ad Hoc Project Management
Formal Application of Project Management
Institutionalization of Project Management
Management of Project Management System
Optimization of Project Management System

Question 23
The focus is on continuous improvement through incremental advancements of existing practices and by innovations using new technologies and methods is established in which of the following Maturity Model Levels?

Ad Hoc Project Management
Formal Application of Project Management
Institutionalization of Project Management
Management of Project Management System
Optimization of Project Management System

Question 24
Which of the follow percentages is the authors' estimate of project-driven organizations that have been implementing some form of oversight for several years?

95%
90%
85%
80%
75%

Question 25
During which of the following phase gates would the question of "Are time, costs, and scope performances within acceptable limits?" be ed?

Proposal
Screening and selection
Implementation
Progress evaluation
Closure.

Business Management, Management Studies

  • Category:- Business Management
  • Reference No.:- M92088351
  • Price:- $25

Priced at Now at $25, Verified Solution

Have any Question? 


Related Questions in Business Management

Oracle has two important files that need to be in place for

Oracle has two important files that need to be in place for an installation. D iscuss the Oracle tnsnames.ora and listener.ora files and their purpose.

1 how could a manager educate stakeholders on effective

1) How could a manager educate stakeholders on effective risk management? 2) How risk management should relate to the scope, schedule and budget?

What are the similarities of organizational and

What are the similarities of organizational and environmental pressures?

A friend says he expects to make money in the stock market

A friend says he expects to make money in the stock market using what he learned in economics about the effect of currency values on exports. When the dollar falls in value he will invest in corporations that sell export ...

Do you think the mountain view situation is representative

Do you think the Mountain view situation is representative of GM's supply chain, and other automotive supply chains in general? Is it also representative of supply chains in other industries as well? What are the implica ...

Would it help if a non-profit that aims to help the less

Would it help if a non-profit that aims to help the less fortunate lobbied with the United Nations and other international organizations to make the governments in some of the countries to spend a certain percentage of t ...

A cartel is branch of an oligopoly there are still a

A cartel is branch of an oligopoly. There are still a handful of large firms and many smaller firms. For instance, the diamond industry and the petroleum industries are examples are oligopolies. However, the main differe ...

How can transportation and logistics policies utilize

How can transportation and logistics policies utilize resources and can the polices favour the business?

1 please illustrate the process of sorting the sequence 3 1

1. Please illustrate the process of sorting the sequence 3, 1, 4, 5, 9, 2, 6, 5 using bubble sort. 2. Please illustrate the process of sorting the sequence 3, 1, 4, 1, 5, 9, 2, 6 using merge sort.. 3. Please determine th ...

What are the differences between the federal deficit and

What are the differences between the Federal deficit and Federal Debt? How does a government budget deficit affect the economy, specifically the unemployment rate and job creation? Identify two periods in recent history ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As