Assignment

Instructions: You may use the software tools available to you, including Microsoft Excel, Word, PowerPoint, and Project, as needed. Please include your answers and other results in this document in a different color.

1.The following are data for two IT projects for a new database system. Prepare a spreadsheet for two projects, using the following data. Amounts are in thousands of dollars. Calculate the NPV for each. (Please assume a Discount Rate of 10%)

 

Year 1

Year 2

Year 3

Year 4

Year 5

Total

Project 1







Benefits

$0

$2,000

$3,000

$4,000

$5,000

tbd

Costs

$5,000

$1,000

$1,000

$1,000

$1,000

tbd

Cashflow

($5,000)

$1,000

$2,000

$3,000

$4,000

$5,000

Project 2







Benefits

$2,000

$3,000

$5,000

$3,000

$1,000

tbd

Costs

$2,000

$2,000

$2,000

$2,000

$1,000

tbd

Cashflow

$0

$1,000

$3,000

$1,000

$0

$5,000

2. Prepare a precedence diagram for the following tasks. All tasks have a finish-to-start relationship.

Task

Duration

Preceded By

Followed By

A

1

None

B, C, D

B

2

A

E

C

3

A

E, F

D

4

A

G

E

5

B, C

F

F

6

C

H

G

7

D

H

H

8

E, F, G

None

3. Prepare a Gantt chart for the tasks shown for question 2. (This can be hand drawn if you have no software to make it, and then you can take a picture of your drawing and included it in this document as an image).

4. Determine the critical path for the tasks shown for question 2.

5. Your company is planning to launch a new IT project starting July 1 that will last one year. You estimate that you will need one full-time project manager, two full-time business analysts for the first six months, two full-time senior systems analysts for the whole year, four programmers for the months of February-May, and one full-time technical writer for the last three months. Create a stacked column chart using Excel that shows resources by month. Provide appropriate titles, axes labels, and legends.

6. Take the MBTI. There are several websites you can use: www.humanmetrics.com, www.personalitytype.com, and www.kiersey.com. Write a one-page summary discussing your MBTI type and its opposite MBTI type. For example, if you are an INTJ, then its opposite is ESFP. What challenges would you see working with this person on a project? What you think about the MBTI as a team-building tool?

7. Your IT consulting company is trying to decide which of four projects to bid. Information on each is in the table below. Assume that all up-front investments are not recovered, so they are shown as negative profits. Draw a diagram and calculate the expected monetary value (EMV) for each project. Write a paragraph explaining which project(s) you would choose to bid.

Project

Chance of Outcome

Estimated Profit

Project 1

50%
50%

$120,000
-$50,000

Project 2

30%
40%
30%

$100,000
$50,000
-$60,000

Project 3

70%
30%

$20,000
-$5,000

Project 4

30%
30%
20%
20%

$40,000
$30,000
$20,000
-$50,000

8. Your company has a technical support line for customers to call. Create a Pareto diagram based on the information in the following table. Create a spreadsheet using these data. List the most frequent complaint first. Then add a column labeled "% of Total" and another labeled "Cumulative %". Then enter formulas to calculate these items. Then use the Excel Chart Wizard to create a Pareto diagram based on the data. Use the Line - Column on 2 Axis custom type chart so that your resulting chart looks similar to the one in Figure 8-1.

Customer Complaints

Frequency/Week

Customer is on hold too long

90

Customer gets transferred to wrong number

20

Customer gets cut off

50

Service rep cannot answer customer's question

120

Service rep does not follow through as promised

40

Service rep is rude

10

9. Use the following WBS and duration information for a project to build a new website. Prepare a Gantt chart and a precedence diagram. Determine the critical path.

1.

Initiating

1 week

2.

Planning

4 weeks, starting after Initiating ends

3.

Executing

 

 

3.1 Conduct User Interview

6 weeks, starts after Initiating ends

 

3.2 Conduct User Survey

4 weeks, starts midway through User Interviews

 

3.3 Site Content

 

 

 

3.3.1 Develop Templates

12 weeks, starts after User Interviews and User Survey end

 

 

3.3.2 Write Articles

8 weeks, stats anytime after Site Content begins

 

 

3.3.3 Prepare FAQ

2 weeks, starts after User Interviews and User Survey ends

 

3.4 Design Site

8 weeks, starts after User Interviews and User Survey end

 

3.5 Build Site

16 weeks, starts after Design Site ends

 

3.6 Perform Integration Testing

2 weeks, starts after Build Site ends

 

3.7 Conduct Acceptance Tests

2 weeks, starts after Integration Testing ends

4.

Controlling

runs for entire duration of project

5.

Closing

1 weeks, follows Acceptance Testing

10. Using the following information for a one-year software development project, answer the following four questions.
PV = $23,000
EV = $20,000
AC = $25,000
BAC = $120,000

What are the cost variance, schedule variance, cost performance index, and schedule performance index for the project?

How is the project doing? Is it ahead of schedule or behind? Is it under budget or over?

Use CPI to calculate the estimate at completion (EAC)? Is the project performing better or worse than planned?

Use SPI as your guide, how long will it take to finish the project?

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92100746
  • Price:- $45

Priced at Now at $45, Verified Solution

Have any Question?


Related Questions in Operation Management

Conflictdefine functional versus dysfunctional conflict in

Conflict Define functional versus dysfunctional conflict in a work group and explain how you can increase functional conflict and decrease dysfunctional conflict. Develop a response that includes examples and evidence to ...

For this assignment you will need to find 2 articles in

For this assignment, you will need to find 2 articles in business that can help describe what are IT strategic initiative being undertaken by an organization are like. Choose a different organization for each of the arti ...

Coping with problems joe is a little nervous he has just

Coping With Problems Joe is a little nervous. He has just been transferred from another plant to take over a production line. Production is down and there is a serious problem with absenteeism. To make matters worse, the ...

Over 30 years ago michael porter identified a holistic

Over 30 years ago Michael Porter identified a holistic approach to understanding how competitive forces shape strategy. He posited that the only way to truly insulate an organization from underlying economic volatility i ...

You are the contracting officer for an air-to-ground

You are the contracting officer for an air-to-ground missile development program. A contract for pre-production models of the missile was awarded by your predecessor and the contractor is behind schedule. In a program me ...

The ikea case provides an excellent opportunity to apply

The IKEA case provides an excellent opportunity to apply strategic management concepts to a large privately-held company that is expanding into India. IKEA is a Netherlands-based Swedish company with a presence in 44 cou ...

Can you answer for me the following questions about social

Can you answer for me the following questions about social loafing and the three main causes of free-riding. 1. Give a description of the phenomenon of social loafing. 2. Give a description of the phenomenon of free-ridi ...

1 analyzing the bridgestonefirestone and ford motor company

1. Analyzing the Bridgestone/Firestone and Ford motor company, is it sufficient to use the ISO/QS 9000 standards as the main basis of vendor/product selection? 2. What position to these cars company ( 1. Volkswagen, 2. F ...

Research the effect of primary and secondary seat belt laws

Research the effect of primary and secondary seat belt laws on the occurrence of motor-vehicle injuries and fatalities. Explain how epidemiologic studies influenced the development of current seat belt laws. Describe how ...

Please provide a brief paragrap of the key takaways from

Please provide a brief paragrap of the key takaways from each of the following topics: Designing Clear Visuals in business reports Designing Successful Documents and Websites Writing Winning Proposals

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As