Ask Homework Help/Study Tips Expert

Assignment

1- Record your numerical answers (in order) to the nearest tenth of jph. (Enter numbers only):

a. A station with three machines operating in parallel with 20-minute process times (te) at each machine.

b. A balanced line with single-machine stations, all with average processing times (te) of 15 minutes.

c. A line with four single machine stations in series, where the average processing times are: 15, 20, 10, & 12 minutes respectively.

d. A four station line with multi-machine stations A, B, C, & D, where the number of parallel machines are 2, 6 10, & 3 respectively. The average processing times (te) at each station are 10, 24, 40, & 18 minutes respectively (see table below).

Process Line with series stations & parallel machines per station Question (d)

Station 

te(minutes)

te(hours)

Machine jph(1/te)

Machines/ station

Station jph

1

10

0.167

6

2


2

24

0.40

4

6


3

40

0.67

4

10


4

18

0.3

6

3


2- Consider a three station line with single-machine stations 1, 2, & 3. The average natural processing times (t0) at each station are 15, 12, and 12 minutes respectively. However, machine 2 is subject to random failures, which causes its Availability to be only 75%. Assuming 100% Availability for the other 2 stations, find te for station 2 and answer the following questions (see table below for problem summary):

a. Find T0 of this line by adding the effective process times, te's, together and enter to 2 decimal places in the first answer box below (if less than 1, show leading zero).

b. What is bottleneck rate, rb, of the line to two decimal places? Enter the value to 2 decimal places in the second answer box below.

Process Line with series stations with one machine per station

Station/ Machine 

t0(minutes) 

t0(hours) 

te(hours) 

jph (1/te)


1

15

0.25

0.25

4.0


2

12

0.20

?

?


3

12

0.20

0.20

5.0




T=
r=




c. Then use T0 and the bottleneck rate, rb, and calculate W0 to one decimal place for entry into the answer box.

d. If the Availablility of station 2 is reduced to 50%, what is the new critical WIP, W0? (to one decimal place)

e. What happens to the line throughput, TH? Indicate in either the work "up" or "down" (don't show quotation marks).

3-Answer the following questions and enter answers with format indicated into the respective answer boxes:

a. Which is preferable - long, but infrequent machine outages; or, short, but more frequent outages? Answer format: enter either long or short.

b. t0 is the average natural (no detractors) process time at a workstation and is increased to the effective process time te by "detractors" such as machine downtime (availability) and more lengthy setup times between jobs. Calculate te given a t0 = 4 minutes with an Availability of 80% and a setup time of 20 minutes of every 50 jobs. Give your answer in minutes to one decimal place.

c. What is the coefficient of variation CV for the te from (b) and a standard deviation of effective process time at a station of 2.7 minutes. Give answer to two decimal places with a leading zero before the decimal.

d. Is the CV from (c) a low, moderate, or high variability class. Enter low, moderate, or high in answer box.

e. In a high utilization (bottleneck) station, what determines the variability of the flow out of that station? Select either the parts arrival variability or the stationvariability. Enter either arrival or station.

4-Floor-On Ltd., operates a line that produces self-adhesive tiles. This line consists of single-machine stations that are balanced (station rates equal). A Manufacturing Technologist has estimated the bottleneck rate, rb, of the line to be 1,600 cases per 16-hour day, and the raw process time, T0, to be 15 minutes. The actual throughput of the line, TH, averages 1,200 cases per 16-hour day, and cycle time, CT, has averaged 4 hours. Find the following and enter into the respective answer boxes below with the exact format stated:

a. Critical WIP, W0 = rb * T0 to the nearest whole number of cases (enter only the number in the answer box).

b. Actual average throughput, TH, to the nearest whole number of cases per hour (enter only the number, no letters).

c. Actual average work-in-process, using Little's Law: WIP = TH X CT (to the nearest whole number of cases).

d. Best-case Throughput, THbest.

e. Practical-worst-case Throughput, THpwc. (Enter numerical answer to one decimal place).

f. Based on actual TH vs THpwc is the operation considered "lean?" (Answer should be entered as either a yes or a no).

5-This process line has the following overall actual production data as follows:

Average actual throughput TH is 120 jobs per 16-hour production day.

Cycle time CT is 4 hours

Assume 100% machine availability and no setup times so that te is the same as to

Answer the questions after filling in your copy of the table below to find rb and T0:

Process Line with series stations with one or more machines per station

Station/Machine 

Machine rate jph 

te(hours) 

Number of Machines Per Station 

Station Rate jph 

1

12


1


2

5


2

 

3

6


2



T0 =


rb =


1. Use Little's Law to find the average actual WIP (round to nearest whole job and enter in the first answer box below). Continue with next answer in the next respective box.

2. What is bottleneck rate rb as calculated from the slowest jph station in table above? (Enter as number with rounding to nearest whole number)

3. What is the raw process time T0 found from summing the te's from table above (Enter to 2 decimal places with leading zero before the decimal)

4. Calculate the THpwc (Enter to nearest whole number jph - no written characters). Compare with actual to see how it compares (no answer required)

5. Calculate the CTpwc (Show to 2-decimal places in hours - no written characters). Compare with actual to see how it compares (no answer required)

6. Is the operation considered "lean" relative to actual TH vs THpwc? (Answer with either the word yes or the word no).

6-Compute the average capacity in jobs per day (jpd) for the following situations (enter the data in the respective boxes with format indicated):

1. A workstation with 10 machines in parallel each having a mean process time t0 of 2.5 hours. There are two 8-hour shifts. Lunch and breaks take 1.25 hours per shift giving a total productive time of 2 shifts/day *(8 hr/shift - 1.25 hr/shift) = 13.5 hr/day that you can use for converting jph to jpd. (Enter answer in first box to nearest whole job).

2. Same situation as above except that the machines have a mean-time-to-failure of 100 hours with a mean time to repair of 4 hours (use availability formula to find uptime %). And, the machines are set up every 10 jobs with a mean setup time of 3 hours. (Given t0, calculate te taking availability, and setup time into account and convert to jph for the station and then convert to jpd). (Enter into the 2nd box to nearest whole jpd).

3. Same situation as (2) above but factor in worker utilization. Because the operators have to attend training meetings and the like, we cannot plan more than 85% utilization of the workers operating the machines. Compute the capacity taking this factor into account. (Likewise, enter the jpd to nearest whole jpd into the 3rd box below).

4. By considering "practical detractors" how much has the jpd rate dropped from situations 1 to 3 (take the difference and enter to the nearest whole jpd and enter into the 4th box below).

Homework Help/Study Tips, Others

  • Category:- Homework Help/Study Tips
  • Reference No.:- M92247629

Have any Question?


Related Questions in Homework Help/Study Tips

Review the website airmail service from the smithsonian

Review the website Airmail Service from the Smithsonian National Postal Museum that is dedicated to the history of the U.S. Air Mail Service. Go to the Airmail in America link and explore the additional tabs along the le ...

Read the article frank whittle and the race for the jet

Read the article Frank Whittle and the Race for the Jet from "Historynet" describing the historical influences of Sir Frank Whittle and his early work contributions to jet engine technologies. Prepare a presentation high ...

Overviewnow that we have had an introduction to the context

Overview Now that we have had an introduction to the context of Jesus' life and an overview of the Biblical gospels, we are now ready to take a look at the earliest gospel written about Jesus - the Gospel of Mark. In thi ...

Fitness projectstudents will design and implement a six

Fitness Project Students will design and implement a six week long fitness program for a family member, friend or co-worker. The fitness program will be based on concepts discussed in class. Students will provide justifi ...

Read grand canyon collision - the greatest commercial air

Read Grand Canyon Collision - The greatest commercial air tragedy of its day! from doney, which details the circumstances surrounding one of the most prolific aircraft accidents of all time-the June 1956 mid-air collisio ...

Qestion anti-trustprior to completing the assignment

Question: Anti-Trust Prior to completing the assignment, review Chapter 4 of your course text. You are a manager with 5 years of experience and need to write a report for senior management on how your firm can avoid the ...

Question how has the patient and affordable care act of

Question: How has the Patient and Affordable Care Act of 2010 (the "Health Care Reform Act") reshaped financial arrangements between hospitals, physicians, and other providers with Medicare making a single payment for al ...

Plate tectonicsthe learning objectives for chapter 2 and

Plate Tectonics The Learning Objectives for Chapter 2 and this web quest is to learn about and become familiar with: Plate Boundary Types Plate Boundary Interactions Plate Tectonic Map of the World Past Plate Movement an ...

Question critical case for billing amp codingcomplete the

Question: Critical Case for Billing & Coding Complete the Critical Case for Billing & Coding simulation within the LearnScape platform. You will need to create a single Microsoft Word file and save it to your computer. A ...

Review the cba provided in the resources section between

Review the CBA provided in the resources section between the Trustees of Columbia University and Local 2110 International Union of Technical, Office, and Professional Workers. Describe how this is similar to a "contract" ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As