Assignment

1. The Bloomington Bike Company produces two models: the Basic and the Supra. Herb Hoosier, the owner, plans to assemble 15 Basics and 10 Suprasin each week during periods 4 to 8.  Product structure trees for each bike are shown below:

906_1.jpg

 

Develop a materials requirement plan (MRP) for component parts K and W over the next eight weeks. Data on all lead times, current inventory and ordering rules are given below: Scheduled receipts are: Period 1:  20 B's, 18 W's; Period 2:  20 S's, 15 F's. A sample MRP table is provide below.

ITEM

LEADTIME (WKS)

ON HAND

LOT-SIZING RULE

B

2

5

Lot-for-lot

S

2

2

Lot-for-lot

X

1

5

Multiples of25

W

2

2

Multiples of 12

F

1

10

Multiples of 30

K

1

3

Lot-for-lot

Q

1

15

Multiples of 30

M

1

0

Lot-for-lot

 

1

2

3

4

5

6

7

8

Gross requirements

 

 

 

 

 

 

 

 

Schedule receipts

 

 

 

 

 

 

 

 

Projected on hand

 

 

 

 

 

 

 

 

Net requirements

 

 

 

 

 

 

 

 

Planned order receipt

 

 

 

 

 

 

 

 

Planned order release

 

 

 

 

 

 

 

 

1. A ?rm makes car seats for an automaker in two varieties: leather and fabric. The standard labor-hours for these are 1.2 and 1.0 hours, respectively. The seats are made in two work centers, sewing and assembly, where the average percentage of work has been 55 percent for sewing and 45 percent for assembly. The following schedule for the next six weeks is given.

Week

1

2

3

4

5

6

Leather

15

20

18

21

15

13

Fabric

65

60

62

59

65

67

a) Using the CPOF (Capacity Planning Using Overall Factors) approach, calculate the labor-hours needed in each of the two work centers in each week.

b) Suppose the following information is given. Using the capacity bills approach, calculate the labor-hours needed in each of the two work centers in each week.


 

Work Center

Time (hours/unit)

Leather

Fabric

Sewing

0.7

0.6

Assembly

0.5

0.4

Total

1.2

1.0

2. A manufacturing facilityproduces two types of a product: Standard and Deluxe. The process flow for both types of production is shown in the following chart. Both types are first processed through steps A1 and A2.

The Standard then goes through steps A3 and A4 while the Deluxe is processed through steps A5, A6, and A7. Both types finish at A8. The numbers in parentheses indicate the minutes it takes for that activity to process a singleunit.

141_2.jpg

a) Which step is the bottleneck for the Standard products? Which step is the bottleneck for the Deluxeproducts?

b) What is the capacity (measured as units per hour) of the facility to process the Standard products? What is the capacity to process the Deluxeproducts?

c) If 60 percent of the products are Standard and 40 percent are Deluxe, what is the average capacity (measured as units per hour) of the facility?

d) Following Part c), if the actual throughput is 3.2 units per hour, what is the utilization of each step (A1-A8)?

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92260905
  • Price:- $60

Priced at Now at $60, Verified Solution

Have any Question?


Related Questions in Operation Management

1 who are the key stakeholders affected by the united

1. Who are the key stakeholders affected by the United Airlines scandal - What is the result? 2. Examine how the concept "Translate Thought Into Action" has bearing on the relationship between business strategy and opera ...

You wish to compete in the super premium hamburger

You wish to compete in the super premium hamburger semi-fast food restaurant market. The task is to determine the wants of the super premium market and the attributes/hows to be met by their firm. Use the house of qualit ...

A a cook is preparing vegetables to put into a soup there

A. A cook is preparing vegetables to put into a soup. There are three tasks: She requires 5 minutes to cut up the carrots, 10 minutes to chop the onions, and 3 minutes to cut up the parsnips in order to fulfill the requi ...

Consistent with the landlordrsquos implied warranty of

Consistent with the landlord’s implied warranty of habitability, can the landlord and tenant agree in a lease that the tenant bear any and all expenses to repair the refrigerator, the stove, and the microwave? Under what ...

1 research the travel act and the fcpa explain how the sec

1. Research the Travel Act and the FCPA Explain how the SEC could file charges under the FCPA if this was not a bribery case involving a foreign government 2. What would you do if your supervisor directed you to bribe . ...

Typically mcdonaldrsquos produces menu items in advance of

Typically, McDonald’s produces menu items in advance of customer orders based on anticipated demand. In contrast, Burger King produces menu items only in response to customer orders. Which system (MRP-II or lean manufact ...

Select a middle eastern organization and review its vision

Select a Middle Eastern organization and review its vision, mission, and strategy. Then, analyze the organization and review its performance management system and its performance appraisal process. Additionally, examine ...

Debate the advantages and drawbacks of using debt financing

Debate the advantages and drawbacks of using debt financing compared to equity financing to meet the financial needs of a start-up. Choose at least two examples of each type to compare and contrast.

How the law affects managers and management in general this

how the law affects managers and management, in general. This is important for you to know as employees as well as potential future employers. Important note: One may not follow the law, but one should be aware of the ra ...

Answer the following 3 questions on building team

Answer the following 3 questions on building Team Cohesiveness: How to Build Team Cohesiveness Schedule social time together. Get agreement on group goals. Focus attention on competition with outside groups. Reward membe ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As