Q. ABC Company wants to bid on job installing 30 swimming pools. This will be a new line of work for this company. They believe there will be a learning effect for this job. After reviewing time records from a similar type of activity, they convinced which an 80% curve is appropriate. They estimate which the first job will take their crew 7 days to install. Elucidate how many days should ABC Company budget for:
Show your calculations
a) The first 10 installations?
b) The second 10 Installations?
c) The final 10 Installations?
d) The 30th installation?