A vertical curve passes over an existing underground waterline that runs perpendicular to the roadway at station 20+91.00. The top of the waterline is at elevation 407.50 feet. The minimum clearance between the roadway and the waterline must be 6 feet. The PVI is located at station 19+00.00 with elevation 420.50 feet. The design speed of the curve is 55 mph, G1 is +3%, and G2 is -3.0%.

a. Calculate the minimum length of this curve.

b. Determine if the clearance between the vertical curve and the waterline is adequate.

c. If the clearance is not adequate in this type of case what modification to L would be required to increase the clearance?

Discuss possible ramifications of making this modification. (Do not need to do any calculations in part c).

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91627337

Have any Question?


Related Questions in Operation Management

Technology solutions in this section you will discuss how

Technology Solutions: In this section, you will discuss how each of the two technologies meets the technology requirements that you identified in section II. Use your decision matrix to guide your responses. A. Technolog ...

Madoff investments securities llc 1 introduction amp

Madoff investments securities , LLC 1. Introduction & history of the company 2. Statements of facts ( what was the ethical dilemma , who were the stakeholders affected ? etc. 3. Important people involved /implicated in t ...

1 compute the takt time minutes per unit for a system given

1. Compute the takt time (minutes per unit) for a system given the following data: There is a single worker per shift with a total time per shift of 460 minutes. There is/are 1 shift(s), and workers are given two 5 minut ...

Annual demand for an item is 6500 units with the cost per

Annual demand for an item is 6,500 units with the cost per unit at $380. The inventory holding rate is 18% and the ordering cost is $15.00 per order. The standard deviation of daily demand is 7 units. Assume 261 days in ...

You are managing a project to film 5 promotional videos to

You are managing a project to film 5 promotional videos to be posted on Youtube, to promote a company. Your project has a Budget at Completion (BAC) of $12,000. One of the tasks on the critical path is to arrange a filmi ...

1 provide the relationship between the scheduling and

1. Provide the relationship between the scheduling and project management in illustrates its uniqueness 2. How does on determine whether or not they have standing to appear in critical court? 3. How would you design a te ...

Herzbergrsquos two-factor theory speaks to issues relevant

Herzberg’s two-factor theory speaks to issues relevant in both employee compensation and benefits as it discusses why people choose a workplace, as well as what keeps employees satisfied and committed to their work. For ...

Rays satellite emporium wishes to determine the best order

Ray's Satellite Emporium wishes to determine the best order size for its best-selling satellite dish (model TS111). Ray has estimated the annual demand for this model at 800 units. His cost to carry one unit is $120 per ...

What kinds of things might explain the race and sex

What kinds of things might explain the race and sex discrimination given the existence of HP ( HP includes race, creed color,religion,gender, sexual orientation, national origin,disability, age, and coverage vetarn statu ...

1 what is the advantage of using a composite of indicators

1. What is the advantage of using a composite of indicators (such as the 10 leading indicators) over simply using an individual indicator? 2. Do leading indicators tend to give longer warnings before peaks or before trou ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As