A set of jobs wants to be scheduled through a single employment center. The details of the jobs in expressions of their processing times and due dates are given below
Jobs 1 2 3 4 5 6
Processing times 4 6 10 12 3 9
Due dates 21 14 15 22 3 12
Utilize different scheduling rules to achieve different objectives as listed below as well as provide a rationale for each of the responses 1. Minimalize the throughput time. 2. Minimize the lateness of all jobs 3 Minimize the prematurity of all jobs 4 Minimize the number of jobs that are late beyond their due dates.