A project to develop technology training seminars is 5 days behind schedule at day 65.

It had a planned cost of exist735,000 for this point in time, but the actual cost is only exist550,000. Estimate the schedule and cost variances.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92760918

Have any Question?


Related Questions in Operation Management

1 relate the importance of keeping records2 compare and

1. Relate the importance of keeping records. 2. Compare and contrast receipts and invoices. 3. Briefly describe the difference between cash and accrual methods of record keeping. 4. Briefly discuss the fundamental purpos ...

Enron basically created a market in energy gambled with it

Enron basically created a market in energy, gambled with it and manipulated it for their gain. They were able to get to the top of their industry by challenging their employees to “ask why” in order to find creative solu ...

You are managing a project to film 5 promotional videos to

You are managing a project to film 5 promotional videos to be posted on Youtube, to promote a company. Your project has a Budget at Completion (BAC) of $12,000. One of the tasks on the critical path is to arrange a filmi ...

The bijou theater shows vintage movies customers arrive at

The Bijou Theater shows vintage movies. Customers arrive at the theater line at the rate of 100 per hour. The ticket seller averages 30 seconds per customer, which includes placing validation stamps on customers' parking ...

1 explain the major management challenges in developing

1. Explain the major management challenges in developing international information systems. Describe the three steps of a management strategy. Are there any disadvantages? 2. How does one determine whether or not they ha ...

You have a job assisting the medical director at a family

You have a job assisting the Medical Director at a Family Medical Clinic in New York City. The Medical Director is concerned about the long wait times of patients visiting the clinic and would like to improve operations. ...

Charlies pizza orders all of its pepperoni olives anchovies

Charlie's Pizza orders all of its pepperoni, olives, anchovies, and mozzarella cheese to be shipped directly from Italy. An American distributor stops by every six weeks to take orders. Because the orders are shipped dir ...

Explain how the healthcare administrator can ensure that

Explain how the healthcare administrator can ensure that inventory management and the material management cycle is effective (both for patients welfare and the organizations profit margin). Make sure to include the who, ...

1 please bullet the quality issues for chipolte for past 5

1. Please bullet the Quality issues for Chipolte for past 5 years. Do not overdo Brainstorm of Gps watches using each of the categories in the market matrix Cycle time is a useful measure of process performance because a ...

You took one job over another mostly because the salary is

You took one job over another mostly because the salary is higher but also because it's in your hometown. You have twin sisters in middle school and want to be close by; your parents are in the process of divorcing. Writ ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As