A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low.

A major milestone has been reached where the first two activities have been totally completed and the third activity is 55% complete. the planners were only expecting to be 46% through the third activity at this time. the first activity involves prepping the site for the bridge. It was expected to cost $1330000 and it was done for only $1295000. the second activity was the pouring of the concrete.

This was expected to cost $11000000 but was actually done for $11200000. the third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8550000. To date they have spent $6900000 on the superstructure.

Calculate the cost and schedule variance and the schedule and cost performance indexes for the project.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92760931

Have any Question?


Related Questions in Operation Management

Part 1write 200-300 words that respond to the following

Part 1 Write 200-300 words that respond to the following questions with your thoughts, ideas, and comments. Be substantive and clear, and use examples to reinforce your ideas. The line managers in the production departme ...

Singapore cars are the worldrsquos most expensive a main

Singapore cars are the world’s most expensive. A main reason is deliberate government policy. Buyers must pay several levies on top of the basic price for a car, including the “Additional Registration Fee” (ARF) and “Cer ...

Case study how to lose 2 billion dollarsraoul demers was a

Case Study: How to Lose 2 Billion Dollars Raoul Demers was a junior level trader on the derivatives desk in the London branch of a global Swiss bank. Previously, he had worked as a trade compliance analyst in the Geneva ...

Answer the following questions question 1 identify and

Answer the following Questions : QUESTION 1 : Identify and discuss the three building blocks of organizational structure. QUESTION 2 : What is the relationship between a company's corporate-level strategy and its busines ...

1 what were hyatt hotels corporationrsquos motives in

1. What were Hyatt Hotels Corporation’s motives in expanding its brand portfolio? 2. What are HHC's motives in choosing an internationalization strategy for its lower category Hyatt Place brand? 3. What modes of entry mi ...

A company making tires for bikes is concerned about the

A company making tires for bikes is concerned about the exact width of their cyclocross tires. The company has a lower specification limit of 22.7 mm and an upper specification limit of 22.9 mm. The standard deviation is ...

1 why is a strong emotional bond with the company

1. Why is a strong emotional bond with the company especially important in times of change? What specific steps can leaders take to create such a bond? 2. Concerns of JIT: What do you think can be the top managers' conce ...

1 inspection criteria 10 marks explain the inspection

1. Inspection Criteria 10 marks Explain the inspection process that you would implement for your product or service. When would you inspect the product, where would you inspect the product? 2. What is the relationship be ...

The senior executives of an oil company are trying to

The senior executives of an oil company are trying to decide whether or not to drill for oil in a particular field in the Gulf of Mexico. It costs the company $1,000,000 to drill in the selected field. Company executives ...

1 explain how conflict of interests can arise in a

1. Explain how conflict of interests can arise in a profession. Explain the ethical duties regarding such professionals. 2. Why is the length of the product life cycle important for strategy formulation? 3. How are manag ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As