A project network has two paths running through it. The first path has an expected length of 10 days and a variance of 2 days. The second path has an expected length of 11 days and a variance of 1 day. What is the probability that this project will require more than 14 days to complete?

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91574481

Have any Question?


Related Questions in Operation Management

Virtual product development vpdthe stage gate product

Virtual Product Development (VPD) The Stage Gate Product Development Process was developed during the 1980’s by Dr. Cooper. Many functional societies, highly innovative management consultants and individual company drive ...

1 goodwill is an example of a tangible assettruefalse2

1. Goodwill is an example of a tangible asset. True False 2. Inventory is an example of a tangible asset. True False 3. An income statement method of business valuation focuses more on cash flow than asset value. True Fa ...

The dine corporation is both a producer and a user of brass

The Dine Corporation is both a producer and a user of brass couplings. The firm operates 220 days a year and uses the couplings at a steady rate of 4400 per year. Couplings can be produced at a rate of 370 per day. Annua ...

After reading consumer car guides and receiving advice from

After reading consumer car guides and receiving advice from family and friends, Aysha has chosen the new car she would like to purchase. She now wants to research her financing options to choose the best way to pay for t ...

Purposethis exercise can improve your understanding of

Purpose This exercise can improve your understanding of various strategies by giving you experience in classifying strategies. This skill will help you use the strategy-formulation tools presented in Chapter 6 of Strateg ...

Mcdonalds needs to have a new sales inventory and service

Mcdonalds needs to have a new sales, inventory and service system designed. You have conducted some interviews and reduced requests down to the following key capabilities of the system: (1) Customer Will order food and m ...

Prior to completing this assignment review your prior

Prior to completing this assignment, review your prior research and course submissions related to the company you selected for research in Week 2's Environmental Scanning interactive assignment. Ensure that you have inco ...

1 the variability of the supply chain demand has been

1. The variability of the supply chain demand has been identified as one of the main factors that are difficult to predict. What does this mean to a nations military operations? 2. What are the most significant challenge ...

An electronics firm is considering two different

An electronics firm is considering two different manufacturing processes to make a new product. The first process is less capital-intensive, with fixed costs of $100,000 per year and variable costs of $1,400 per unit. Th ...

Submit a two page proposal for your final projectthe final

Submit a two page proposal for your final project. The final project will be to research, propose or review a sustainability project within a company you picked. The proposal should be in the form of a business plan that ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As