A project has the activities and activity times (days) listed below. Determine the probability that the project will require less than 15 days from start to finish.
Formulas:
Path mean = ? (expected times of activities on the path)
Path standard deviation = ,where is the standard deviation for activity i on the path.
Z=(Specified time - Path mean)/Path standard deviation.