A project consists of activities A, B, C, D, E, F, and G. The precedence relationships and the estimated times to complete each activity are given below: Activity Preceding Activity Estimated Time (in days) A - 12 B A 5 C A 10 D A 3 E D 3 F C, D 7 G E, F 5 Additionally, activity ‘B' can start after 2 days work has been completed on activity ‘A' and activity C can start after 6 days work has been completed on activity ‘A'. Activity G can start only after 3 days have elapsed after the completion of activity ‘E'. Draw an Activity on Node Network for this project. Find the ES, EF, LS, LF, TF and AF for each activity assuming that the 36 days are available to complete the project. Identify the critical activities using the TF calculated by you. Draw a Gantt chart showing all the activities as bars from ES to EF. Plot the staffing requirement plot showing staffing requirements for each day assuming each activity requires one person working on it. Show how you can smooth out the staffing requirements by taking advantage of TF and AF.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M9605386

Have any Question?


Related Questions in Operation Management

Consider an invenotry model for a product where the demand

Consider an invenotry model for a product where the demand is constant at rate 12 per unit time. Assume that once an order of size y is placed, units arrive at a rate of 20 unit per time. Suppose the cost of placing and ...

1 is social class really an invisible difference or are

1. Is social class really an invisible difference or are there ways that people often deduce other’s social class origins? What can be the effect of this in job interviews, work-related social situations, and so on? 2. G ...

Suburban homes construction project quality management plan

Suburban Homes Construction Project Quality Management Plan (QMP) Prepare a quality management plan using the elements described in the PMBOK 6e (Section 8.1.3.1) for the Suburban Homes Construction Project. Content Over ...

Cornell cookery inc cci needs some metallic pan liners for

Cornell Cookery Inc. (CCI) needs some metallic pan liners for its products. The current supplier accepts large orders but is only able to supply 5000 liners/day. The current supplier charges 0.47 $/liner. CCI plans an an ...

Format to followintroductiondefinitionsshow

Format to follow Introduction definitions, show understanding give examples to illustrate your answer - MENA region /business/ is higher level explain conclude cite sources if quoted - but not essential approx 250 words ...

Eminent domain is the power of a governmental body

Eminent Domain is the power of a governmental body (municipality, county, etc) to take personally owned real estate forpublic use for just compensation. Issues of fairness often arise when the government takes private pr ...

This weeks lesson discussed the stages of moral development

This week's lesson discussed the stages of moral development as well as a variety of moral intensity factors. Consider and comment on the following questions: 1. Identify one well-known person today (politician, celebrit ...

According to porter faced with pressures to gain market

According to Porter faced with pressures to gain market share or enamored with innovation for its own sake, managers can spark new kinds of competition that no incumbent can win. Consequently , smart strategists focus up ...

Fully answer the assigned questions in narrative third

Fully answer the assigned questions in narrative, third person format. The paper consist of 1200 WORDS. Also, include at least three (3) scholarly sources in your responses. Paper must be completed in APA format. NO PLAG ...

For each of the four situations noted what organizational

For each of the four situations noted, what organizational concepts apply? Identify the concept and explain the related problem. Two welders, unable to get a decision from their supervisor, requested time off. One welder ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As