A product is made by activities performed sequentially through three work stations (WS#1, WS#2, WS#3).

At the beginning of the shift, WS#1 is supplied with all the raw materials it might need for the day. Ws#1 can therefor work continuously, beginning on the next item as soon as it finishes the current item. The time it takes to complete the activities in WS#1 is distributed uniformly, with a minimum time of 4 minutes and a maximum time of 6 minutes.

WS#2 begins the shift with nothing and can complete its activities only as WS#1 provides its work-in-progress. The time it takes to complete the activities in WS#2 is : 20% probability of 4 minutes; 50% probability of 5 minutes; and 30% probability of 6 minutes.

WS#3 begins the shift with nothing and can complete its activities only as WS#2 provides its work-in-progress. The time it takes to complete the activities in WS#3 is distributed normally with a mean of 5 minutes and a standard deviation of 1.8 minutes.

a) Construct a simulation in EXCEL for this production line. Determine the number of items that can be produced in an 8 hour shift. Run the simulation three times. How many items are produced for each simulation?

b) What is the total amount of idle time (waiting time) in WS#2 for the 8 hour shift?

C) What is the total amount idle time ( waiting time) in WS #3 for the 8 hour shift?

Business Management, Management Studies

  • Category:- Business Management
  • Reference No.:- M91788556
  • Price:- $30

Priced at Now at $30, Verified Solution

Have any Question?


Related Questions in Business Management

Resource allocation problemfor product a a 10 increase in

Resource Allocation problem For product A, a 10% increase in investment increases the quantity sold by 5% whereas for product B, a 10% increase in investment increase quantity sold by 20%. The current unit sales level of ...

Given a tree design an algorithm to find the maximum path

Given a tree, design an algorithm to find the maximum path length between two vertices. Analyze its time complexity.

The following table shows the distribution of grades on a

The following table shows the distribution of grades on a mathematics exam:  Grade Number of Students 0-59 5             60-69 12             70-79 28             80-89 14             90-100     9             Use this in ...

Describe different networking methods and the advantages

Describe different networking methods and the advantages and disadvantages of them?

Example of a company using forecasting for operations

Example of a company using forecasting for operations management in supply chain management?

Provide an example of an organization that has achieved

Provide an example of an organization that has achieved competitive success through planning and provide an example of an organization that has failed to achieve competitive success as the result of failed planning.

What are key factors that must be planned prior to arriving

What are key factors that must be planned prior to arriving to the contingency location?

Considera firm that faces thefollowingexpectedfuture

Consider a firm that faces the following expected future marginal product of capital: MPKf =1000- 2K Where MPKf is the expected future marginal product of capital and K is the capital stock. The price of capital, pk, is ...

Please help with the information for coors vs anheuser

Please help with the information for Coors vs Anheuser Busch 1977. performance data.

What resources are you most likely to use for research in a

What resources are you most likely to use for research in a workplace? Discuss secondary resources, and primary resources including observation and surveys. What is a credible resource?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As